Will the Minister advise whether the Future Hospital team were represented by 39 Essex Chambers during the planning applications submitted for the new General Hospital; and, if so, will he state on how many occasions their services were used and what fees were paid on each such occasion?
Answer
Christiaan Zwart, a barrister at 39 Essex Chambers, assisted the Future Hospital Team on two occasions in connection with planning applications PP/2017/0990 and planning application PP/2018/0507.
The costs, including disbursements, on each occasion were: PP/2017/0990 £11,991.60