This content has been automatically generated from the original PDF and some formatting may have been lost. Let us know if you find any major problems.
Text in this format is not official and should not be relied upon to extract citations or propose amendments. Please see the PDF for the official version of the document.
STATES OF JERSEY
PROPOSED GOVERNMENT PLAN 2023- 2026 (P.97/2022): TWENTIETH AMENDMENT
HOSPITAL FUNDING
Lodged au Greffe on 28th November 2022 by the Council of Ministers
STATES GREFFE
2022 P.97 Amd.(20)
PROPOSED GOVERNMENT PLAN 2023-2026 (P.97/2022): TWENTIETH AMENDMENT
____________
1 PAGE 2, PARAGRAPH (b) –
After the words "those revised approvals" insert the words ", except that –
- To refer to their Act of 7th October 2021, in which they approved the funding of Our Hospital through borrowing (external financing), and to agree that such approval extends to the funding of ongoing work on the development of future healthcare facilities during 2023; and
- in Summary Table 2, the "Borrowing for Our Hospital" should be renamed "Borrowing for Healthcare facilities", and the maximum amount which may be borrowed for these purposes be set at £90,071,000, with the change to approval in Summary Table 2 amended to £- 665,929,000 with the figure in each of the columns headed 2023, 2024, 2025 and 2026 in Summary Table 2 to be amended accordingly to reflect this change".
2 PAGE 2, PARAGRAPH (c) –
After the words "of the Law" insert the words ", except that, in Summary Table 3, the transfer from the Strategic Reserve to the Consolidated Fund should be amended as follows –
- The transfer for Hospital capital should be amended to £51,500,000 for 2023 and zero in all future years; and
- The transfer for Hospital borrowing should be amended to £4,200,000 in each of 2023 and 2024, £3,900,000 in 2025 and £3,500,000 in 2026".
3 PAGE 2, PARAGRAPH (d) –
After the words "to the Report" insert the words ", except that in Summary Table 4 –
- the Total Project Approval for Our Hospital shall be amended to £77,116,000 with the Change amended to £-727,384,000; and
- the following row shall be added to the end of the table –
Spons Supply Previous Total Project
£'000 Dept Dept Approval Approval Change Healthcare facilities1 HCS IHE - 60,360 60,360
4 PAGE 2, PARAGRAPH (e) –
After the words "of the Report" insert the words ", except that -
1 Includes £8,860,000 spent in 2022 on Les Quennevais under Our Hospital Head of Expenditure
- in Summary Table 5i, the Head of Expenditure for Our Hospital – Financing Costs should be deleted and replaced with the following –
Head of £'000 Income Expenditure Expenditure Healthcare facilities - financing
costs - 4,200 4,200
- in Summary Table 5ii, the Head of Expenditure for Our Hospital should be deleted and replaced with the following –
Major Sponsor Supply 2023 £'000 Project Department Department Estimate Healthcare facilities M HCS IHE 51,500
5 PAGE 2, PARAGRAPH (i) –
Designate the existing paragraph as new paragraph (j) and insert the following paragraph as paragraph (i) –
i) "to refer to their act of 7th October 2021, in which they agreed to amend the Strategic Reserve Fund policy, so as to allow the Fund to be used to support the delivery of Our Hospital and to agree that the policy should be amended to allow the Fund to also be used to support the ongoing work on the development of future healthcare facilities proposed to be undertaken during 2023 and the borrowing costs for such work.
6 PAGE 2, PARAGRAPH (i) –
After the words "Appendix 3 to the Report" insert the words
", except that page 69 shall be amended accordingly to reflect the ongoing work on the development of future healthcare facilities during 2023,".
COUNCIL OF MINISTERS
Note: After this amendment, the proposition would read as follows –
THE STATES are asked to decide whether they are of opinion
- to approve the estimate of total States income to be paid into the Consolidated Fund in 2023 as set out in Appendix 2 – Summary Table 1 to the Report, which is inclusive of the proposed taxation and impôts duties changes outlined in the Government Plan, in line with Article 9(2)(a) of the Law;
- to approve the proposed Changes to Approval for financing/borrowing for 2023, as shown in Appendix 2 – Summary Table 2 to the Report, which may be obtained by the Minister for Treasury and Resources, as and when required, in
line with Article 9 (2)(c) of the Law, of up to those revised approvals except that –
- to refer to their Act of 7th October 2021, in which they approved the funding of Our Hospital through borrowing (external financing), and toagree that such approval extends to the funding of ongoing work on the development of future healthcare facilities during 2023; and
- in Summary Table 2, the "Borrowing for Our Hospital" should berenamed "Borrowing for Healthcare facilities", and the maximumamount which may be borrowed for these purposes be set at £90,071,000, with the change to approval in Summary Table 2 amended to £- 665,929,000 with the figure in each of the columns headed 2023, 2024,2025 and 2026 in Summary Table 2 to be amended accordingly to reflectthis change.
- to approve the transfers from one States fund to another for 2023 of up to and including the amounts set in Appendix 2 – Summary Table 3 in line with Article 9(2)(b) of the Law, except that, in Summary Table 3, the transfer from theStrategic Reserve to the Consolidated Fund should be amended as follows –
- The transfer for Hospital capital should be amended to £51,500,000 for2023 and zero in all future years; and
- The transfer for Hospital borrowing should be amended to £4,200,000 ineach of 2023 and 2024, £3,900,000 in 2025 and £3,500,000 in 2026".
- to approve each major project that is to be started or continued in 2023 and the total cost of each such project and any amendments to the proposed total cost of a major project under a previously approved Government Plan, in line with Article 9(2)(d), (e) and (f) of the Law and as set out in Appendix 2 - Summary Table 4 to the Report, except that in Summary Table 4 –
- the Total Project Approval for Our Hospital shall be amended to £77,116,000 with the Change amended to £-727,384,000; and
- the following row shall be added to the end of the table –
Spons Supply Previous Total Project
£'000 Dept Dept Approval Approval Change Healthcare facilities2 HCS IHE - 60,360 60,360
- to approve the proposed amount to be appropriated from the Consolidated Fund for 2023, for each Head of Expenditure, being gross expenditure less estimated income (if any), in line with Articles 9(2)(g), 10(1) and 10(2) of the Law, and set out in Appendix 2 – Summary Tables 5(i) and (ii) of the Report, except that
–
in Summary Table 5i, the Head of Expenditure for Our Hospital – Financing Costs should be deleted and replaced with the following –
Head of £'000 Income Expenditure Expenditure
2 Includes £8,860,000 spent in 2022 on Les Quennevais under Our Hospital Head of Expenditure
Healthcare facilities - financing
costs - 4,200 4,200
- in Summary Table 5ii, the Head of Expenditure for Our Hospital should bedeleted and replaced with the following –
Major Sponsor Supply 2023 £'000 Project Department Department Estimate Healthcare facilities M HCS IHE 51,500
- to approve the estimated income, being estimated gross income less expenditure, that each States trading operation will pay into its trading fund in 2023 in line with Article 9(2)(h) of the Law and set out in Appendix 2 – Summary Table 6 to the Report;
- to approve the proposed amount to be appropriated from each States trading operation's trading fund for 2023 for each head of expenditure in line with Article 9(2)(i) of the Law and set out in Appendix 2 – Summary Table 7 to the Report;
- to approve the estimated income and expenditure proposals for the Climate Emergency Fund for 2023 as set out in Appendix 2 – Summary Table 8 to the Report;
- to refer to their act of 7th October 2021, in which they agreed to amend theStrategic Reserve Fund policy, so as to allow the Fund to be used to support the delivery of Our Hospital and to agree that the policy should be amended to allowthe Fund to also be used to support the ongoing work on the development of future healthcare facilities proposed to be undertaken during 2023 and theborrowing costs for such work.
- to approve, in accordance with Article 9(1) of the Law, the Government Plan 2023-2026, as set out at Appendix 3 to the Report, except that page 69 shall beamended accordingly to reflect the ongoing work on the development of futurehealthcare facilities during 2023,".
REPORT
Background
The Council of Ministers does not dispute that there is a compelling case to replace the existing health estate. It is recognised that buildings are deteriorating, and that the standard of these facilities may, over time, start to compromise the delivery of health services.
The Council stands together in acknowledging that new, modern and fit for purpose health and care facilities are needed, and high-quality, safe facilities should be delivered as soon as is reasonably practicable. In addition, there is a strong consensus that whilst any new facilities are being delivered, the delivery of safe health and care services in the interim should not be compromised.
However, it cannot be overlooked that current cost estimates in respect of the proposed single-site single-phase scheme at Overdale are in excess of the budget approved by the States Assembly for delivering the project. Indeed, that excess is assessed as being significant – between £70 million and £115 million more than the approved figures and so not affordable within agreed limits. Using a phased approach gives us more flexibility and resilience, allowing us to proceed with each phase only when we know we can deliver it, and afford it.
Project review
In response to the current global context of increasing prices of materials, labour and volatile financial markets as a result of the currently unpredictable geo-political situation and the stark fact that the scheme as proposed is not affordable, the Chief Minister commissioned a review of the Our Hospital project as part of her 100-day plan upon taking office. The full review can be found here.
The review, presented to the States Assembly as R.154/2022, provided advice to the Assembly about whether changes can be made to deliver a more affordable and appropriate alternative. The review concluded changes to the project could be made, most notably with respect to increasing affordability by reducing exposure to risk at any one point in time.
In summary, at a very high level, the review concluded that this could be achieved by delivering new healthcare facilities with a phased approach over two or more sites, including Overdale and areas of Kensington Place:
• To mitigate against the risk of entering into one single, significant value contract. Instead, smaller work packages for smaller elements of the project could be commissioned at times when they were considered more affordable in their constituent parts. In turn, it was concluded that local construction firms could have greater opportunity for involvement in these smaller works packages, therefore better supporting the local economy.
• To mitigate against the risk of exposing Jersey to high levels of debt at unfavourable rates of interest – an alternative financing model could allow phases to be financed in associated tranches. This would reduce exposure at any one point and enable the Government of Jersey to be opportunistic in taking advantage of moments to borrow where interest rates are more favourable. However, the financial model is not set. For example, the Minister for Treasury and Resources has identified other funding opportunities for the programme of
work, such as income received above income forecasts and utilising underspends from other areas.
• To reduce the degree of environmental or infrastructure impacts, when compared to a single-site scheme. Jersey has successfully operated multi-site healthcare for many years, in diverse locations and of an appropriate size for our Island. This will deliver a more appropriate service provision – to ensure that given our island context, the broad range of services delivered by Jersey's Health and Community Services continue to be delivered safely on-island.
• To deliver elements of the programme quicker - a phased solution means shorter construction times. As a result, some healthcare facilities, and where possible those most needing replacement, should be operational in a similar timeframe to the existing plans.
Why amend the Government Plan 2023-26?
The proposed Government Plan 2023-26 includes funding to deliver the single-site single-phase Overdale scheme. In recognising that the scheme is no longer affordable, the conclusions of the review, and the anticipated changes in project direction, the States Assembly must note that previously anticipated expenditure on the project will not be as it stands in the proposed Government Plan. Therefore, it must be amended.
Funding will be required to:
• update feasibility studies that will be required to deliver a new delivery framework and programme with better time and cost certainty, with a view to minimising the risks outlined above. These will require expenditure on Government of Jersey team and professional services to develop a revised brief, early designs and a project programme and plan.
• continue the development of the former Les Quennevais School into a health and care facility, into which services can be relocated from Overdale during construction of that site or for other healthcare services. Although no future direction has been settled, there is an opportunity to retain this site as a delivery space for health and care services in the longer term beyond the construction of new facilities at Overdale, which may fit into a future model of care for Jersey.
• transfer the land at Kensington Place from Andium homes as a strategic purchase to enable the delivery of a multi-site facility.
Further to these initial activities, it is intended that further Propositions will be brought forward by the Council of Ministers asking the States Assembly to consider substantive financing and funding models to deliver new health and care facilities for Jersey as part of a programme of works, supported by designs and a robust case for delivery.
Finances and borrowing
The required changes to the Government Plan are set out below. The revised Summary Tables reflecting the amendment are included at Appendix 1 to this report. In addition, Appendix 2 to this report sets out the revised wording in the Government Plan (page 69) for the hospital project, including revised financial tables.
Capital costs
As an interim step, this Government Plan includes a new head of expenditure for healthcare facilities to replace the previous head of expenditure for Our Hospital. This will allow work on revised plans for new healthcare facilities to continue during 2023,
in advance of substantive financing and funding models being brought to the States Assembly. The new head of expenditure covers the following areas of expenditure:
|
|
|
| £'000 |
|
Healthcare facilities - Les Quennevais Healthcare facilities -Strategic purchase of Kensington Place Healthcare facilities - Development of Revised Scheme Total |
|
| 7,000 16,000 28,500 51,500 |
The amendment also changes the total Major Project approval for Our Hospital, to reflect the costs to completion of that project in 2022. The overall expenditure on Our Hospital up to 2021 was £63.3 million. A further £22.7 million is forecast for 2022, meaning total expenditure of £86 million (including £8.9 million on Les Quennevais).
Revenue costs
The Revenue Head of Expenditure for "Our Hospital - financing costs" is replaced with a new Head of Expenditure called "Healthcare facilities – financing costs". The proposed Government Plan included financing costs of £3.05 million for Our Hospital, increasing in future years in line with the profile of spend and borrowing. This is amended to £4.2 million in 2023 and in future years, reflecting changes to the profile and cost of expected borrowing for the proposed 2023 capital works and the borrowing to conclude the work on Our Hospital up to the end of 2022. In line with previous decisions, these costs will be met by transfers from the Strategic Reserve.
Financing
The capital costs in 2023 (£51.5 million) will be funded through short-term borrowing initially utilising the existing and a new Revolving Credit Facility. A longer-term funding strategy will be brought to the Assembly as part of the development of revised proposals for the hospital project. The amounts borrowed will be kept to a minimum by utilising underspends. In line with the previous funding strategy, the borrowing will be credited to the Strategic Reserve and then transferred to the Consolidated Fund.
When added to the borrowing for the Overdale Scheme under existing approvals in 2022, the total borrowing requirement in 2023 is £90 million (which includes £38.6 million borrowing up to the end of 2022).
Conclusion
The single-site Overdale scheme, as proposed, is no longer affordable within approved budget limits.
The Council of Ministers and the States Assembly have an opportunity to adopt a prudent risk management approach to deliver a more affordable project through a different financing model, and by spreading commitment to spend over a longer period, rather than progressing a single large-scale and high-cost scheme with cost estimates for construction outside the forecasts within the Outline Business Case.
As the Minister for Infrastructure put forward in his review, It is time to put aside the public discord of the past and progress at pace, alongside a constructive dialogue with Health-care workers, Clinicians, Scrutiny, Assembly members and all Islanders, including neighbours and interest groups.
Appendix 1 – Revised Summary Tables
Summary Table 2 - Borrowing for 2023
Existing Change to 2023 2024 2025 2026 £'000 Approval Approval Approval Proposed Proposed Proposed Costs of Covid-19 208,520 (208,520) - - - -
Fiscal Stimulus 29,641 (29,641) - - - - Refinancing of past-
480,000 (3,000) 477,000 477,000 477,000 477,000 service liabilities
Housing Bond 250,000 - 250,000 250,000 250,000 250,000 Total Approved
Borrowing (before Our 968,161 (241,161) 727,000 727,000 727,000 727,000 Hospital)
Borrowing for Our Hospital 756,000 | (665,929) | 90,071 | 90,071 | 90,071 | 90,071 |
Total Approved Borrowing 1,724,161 | (907,090) | 817,071 | 817,071 | 817,071 | 817,071 |
| Summary Table 3 - Transfers of monies between States Funds |
|
|
|
£'000 Transfer From 2023 2024 Transfer To Proposed Proposed |
| 2025 Proposed | 2026 Proposed |
Consolidated Fund Climate Emergency Fund 4,400 4,400 4,400 4,400
Strategic Reserve (Pensions
Consolidated Fund 1,790 2,192 2,605 3,028
refinancing)
Health Insurance Fund Consolidated Fund (Revenue) 6,100 4,100 - - Health Insurance Fund Consolidated Fund (Capital) 6,350 5,705 - - Criminal Offences
Consolidated Fund 1,811 777 - - Confiscation Fund
Social Security (Reserve)
Social Security Fund 89,000 - - - Fund
Consolidated Fund (Hospital capital)
|
|
|
| ||||||||
| 51,500 |
|
| - |
|
| - |
|
| - |
|
1,000 | 336 | - | - |
Strategic Reserve Strategic Reserve
Consolidated Fund (Capital repayment)
Consolidated Fund (Hospital borrowing)
|
|
|
| ||||||||
| 4,200 |
|
| 4,200 |
|
| 3,900 |
|
| 3,500 |
|
|
|
|
|
Strategic Reserve
Summary Table 4 - Major Projects
Spons Supply Previous Total Project
£'000 Dept Dept Approval Approval Change Infrastructure Rolling Vote & Regeneration
IHE IHE - 14,715 - Including St. Helier
Sewage Treatment Works IHE IHE 86,235 88,635 86,235 Learning Difficulties - Specialist
HCS IHE 9,350 9,350 9,350 Accommodation
Ambulance, Fire & Rescue Headquarters JHA IHE 24,403 24,403 24,403 Oakfield and Fort Regent Decant IHE IHE 9,402 9,402 9,402 Office Modernisation IHE IHE 3,923 3,923 3,923 Inspiring Active Places - Sports Strategy IHE IHE 814 3,914
MS Foundation COO COO 11,446 10,871
Cyber & Cyber ORI COO COO 14,970 16,358 14,970 Integrated Tech Solution Release 1 & 2 COO COO 54,740 54,740 54,740 ITS Release 3 & 4 COO COO 6,500 6,500 6,500 ITS Release 3 Additional COO COO 1,281 1,281 1,281 Digital Care Strategy HCS COO 16,185 16,185 16,185 Schools Estate #N/A #N/A - - -
Jersey Opera House ECON ECON - 11,731 - Community Fund T&E T&E - 7,000 - Revenue Transformation Programme T&E T&E 9,425 9,425
Our Hospital | HCS | IHE | 804,500 | 77,116 |
| - 727,384 |
|
Healthcare facilities | HCS | IHE | - | 60,360 |
| 60,360 |
|
Summary Table 5i - 2023 Revenue Heads of Expenditure
Head of £'000 Income Expenditure Expenditure
Departmental Expenditure
Cabinet Office 2,780 70,116 67,336 Children, Young People, Education and Skills 21,220 210,908 189,688
Customer and Local Services 10,452 105,755 95,303 Infrastructure, Housing and Environment 31,177 86,682 55,505 Health and Community Services 26,207 274,089 247,882 Jersey Overseas Aid - 17,700 17,700 Justice and Home Affairs 4,530 39,700 35,170 States of Jersey Police 234 27,342 27,108 Ministry of External Relations 290 3,378 3,088 Department for the Economy - 40,264 40,264 Treasury and Exchequer 3,355 70,743 67,388 Past Service Pension Liability Refinancing 174 13,956 13,782 Departmental Expenditure 100,419 960,633 860,214
Non-Ministerial and Other States Bodies
Bailiff 's Chambers 68 2,192 2,124 Comptroller and Auditor General 80 1,158 1,078 Judicial Greffe 2,382 11,509 9,127 Law Officers' Department 237 11,118 10,881 Office of the Lieutenant Governor 107 946 839 Official Analyst 53 738 685 Probation 88 2,732 2,644 States Assembly 68 8,814 8,746 Viscount's Department 826 2,928 2,102 Non-Ministerial and Other States Bodies
3,909 42,135 38,226 Expenditure
Covid-19 Response - 25,211 25,211 Departmental and Non-Ministerial
104,328 1,027,979 923,651 Expenditure
Reserves
Reserve for Centrally Held Items - 43,506 43,506 General Reserve - 29,187 29,187 Reserve Expenditure - 72,693 72,693 Healthcare facilities - financing costs - 4,200 4,200 Revenue Heads of Expenditure Total 104,328 1,104,872 1,000,544
Summary Table 5ii - 2023 Capital and Other Projects Heads of Expenditure
Major Sponsor Supply 2023 £'000 Project Department Department Estimate Feasibility T&E T&E 1,830 Estates
Land Acquisition IHE IHE - Oakfield and Fort Regent Decant M IHE IHE 5,000 Inspiring Active Places - Sports Strategy M IHE IHE 1,300 Office Modernisation M IHE IHE 460 Crematorium CLS IHE - Vehicle Testing Centre IHE IHE 100 Orchard House IHE IHE 449 Other IHE Estate Projects IHE IHE 1,700 Jersey Opera House M ECON ECON 6,270 Elizabeth Castle M ECON ECON 2,027 Learning Difficulties - Specialist
HCS IHE 1,700 Accommodation M
Health Services Improvements Programme HCS HCS 5,000 In-Patient/Support Services Refurbishments HCS HCS 749 New School and Educational Developments CYPES IHE 3,504 Upgrade to CYPES Estate CYPES IHE 13,621 Ambulance, Fire & Rescue Headquarters M JHA IHE 800 Army and Sea Cadets Headquarters JHA IHE 960 Magistrates' Court conversion JG JG 750 Firearms Range SoJP SoJP 1,775 Dewberry House - Sexual Assault Referral
SoJP IHE 2,851 Centre
Prison Improvement Works JHA IHE 2,985
52,001
Infrastructure
Infrastructure Rolling Vote and
IHE IHE 14,715 Regeneration Including St. Helier
Sewage Treatment Works M IHE IHE 11,966 Countryside Access & Wellbeing IHE IHE - Planning Obligation Agreements IHE IHE - Road Safety IHE IHE - Other Infrastructure IHE IHE 2,950
29,631
Information Technology
MS Foundation (M) COO COO 1,300 Cyber & Cyber ORI M COO COO 5,000 Integrated Technology Solution Release 1 &
COO COO 9,778 2 M
ITS Release 3 & 4 M COO COO 2,300 ITS Release 3 Additional M COO COO 17
Other Government Wide IT Projects COO COO 3,399 Revenue Transformation Programme (Phase
T&E T&E 3,105 3)
Digital Care Strategy M HCS COO 5,300 Jersey Care Model - Digital Systems HCS COO 1,050 Next Passport Project JHA JHA 250 Combined Control IT JHA JHA 567 Electronic Patient Records JHA JHA 191 Regulation Group Digital Assets IHE IHE 1,252 Replacement LC-MS system OA OA - Probation/Prison Case Management system Prob Prob 440 Pride Software JG JG - Phoenix Software Visc Visc 300 Court Digitisation JG JG 1,639
35,888
Replacement Assets and Minor Capital
Replacement Assets and Minor Capital IHE IHE 3,930 Fisheries Protection Vessel & Auxiliary
IHE IHE -
Vessels
Replacement Assets and Minor Capital CYPES CYPES 250 Replacement Assets and Minor Capital HCS HCS 3,755 Replacement Assets and Minor Capital SoJP SoJP 200 Replacement Assets and Minor Capital JHA JHA 162 Replacement of Aerial Ladder Platform JHA JHA 768 Replacement Assets and Minor Capital COO COO 3,000
12,065 Community Fund M T&E T&E 1,000 Reserve for Central Risk and Inflation
T&E T&E 8,100 Funding
Total Project Head of Expenditure 140,515
Healthcare facilities | M | HCS | IHE | 51,500 |
Total Project Heads of Expenditure including Healthcare Facilities |
|
|
| 192,015 |
Appendix 2 – Revised Government Plan section
Hospital Project
The review of the Our Hospital project (R.154/2022) was presented to the Assembly on 1st November 2022. The review provided advice to the Assembly about whether changes can be made to deliver a more affordable and appropriate alternative. The review concluded changes to the project could be made, most notably with respect to increasing affordability by reducing exposure to risk at any one point in time.
As an interim step, this Government Plan includes a new head of expenditure for healthcare facilities to replace the previous head of expenditure for Our Hospital. This will allow work on revised plans for new healthcare facilities to continue during 2023, in advance of a detailed budget and financing strategy being brought to the States Assembly.
The budget for healthcare facilities included in this Government Plan enables the project to:
- update feasibilities studies that will be required to deliver a new delivery framework and programme with better time and cost certainty
- Continue the development of the former Les Quennevais School into a health and care facility, into which services can be relocated from Overdale during construction of that site or for other healthcare services.
- transfer the land at Kensington Place from Andium homes as a strategic purchase to enable the delivery of a multi-site facility.
The capital costs, finance costs and borrowing included in the Government Plan are sufficient to enable the above activities to progress in 2023. A full funding strategy will be brought to the Assembly in due course.
A new head of expenditure for development of healthcare facilities is included in the Government Plan and designated as a Major Project.
In line with previous decisions, the borrowing will be held in the Strategic Reserve and transferred to the Consolidated Fund as required. The financing costs will be met from the Strategic Reserve (also in line with previous decisions).
Hospital project
->2022 2023 2024 2025 2026 Estimate £'000 Estimate Estimate Estimate Estimate
Revenue Expenditure
500 Financing Costs - Revenue Expenditure 4,200 4,200 3,900 3,500 500 Total Revenue 4,200 4,200 3,900 3,500
Capital Expenditure
8,860 Healthcare facilities 51,500
77,116 Our Hospital - Capital Expenditure
85,976 Total Capital 51,500 0 0 0
Strategic Reserve Transfers
Strategic Reserve to Consolidated Fund -
(500) (4,200) (4,200) (3,900) (3,500)
Financing Costs
Strategic Reserve to Consolidated Fund -
(38,571) (51,500)
Our Hospital
(39,071) (55,700) (4,200) (3,900) (3,500)
Strategic Reserve Borrowing Proceeds
38,571 Borrowing Proceeds 51,500 38,571 51,500 0 0 0
Table 34: Our Hospital