This content has been automatically generated from the original PDF and some formatting may have been lost. Let us know if you find any major problems.
Text in this format is not official and should not be relied upon to extract citations or propose amendments. Please see the PDF for the official version of the document.
STATES OF JERSEY
LA COLLETTE WASTE MANAGEMENT SITE – DEVELOPMENT PLAN
Lodged au Greffe on 6th April 2023 by the Minister for Infrastructure Earliest date for debate: 23rd May 2023
STATES GREFFE
2023 P.17
PROPOSITION
THE STATES are asked to decide whether they are of opinion −
- to support the short/medium term Plan for Waste Management at La Collette Reclamation Site Phase II to include:
- a combined waste management approach for hazardous waste and inert soils under a ‘La Collette Waste Management Site – Development Plan’, as detailed in drawing 22023-100;
- the formation of the ‘East Headland’ and ‘South Headland’ by deposition of hazardous waste in cells as per plans submitted under application P/2016/1647;
- the formation of the ‘West Headland’ by deposition of inert waste soils in a mound;
- the landscaping and restoration of the East Headland and South Headland as per the plans submitted under application P/2016/1647; and
- the creation of a publicly accessible one-mile-long coastal path around the perimeter of the site once landscaping and restoration is complete; and
- to request that, in the period enabled by the short/medium term plan, the Minister for Infrastructure and the Minister for the Environment develop the long-term plan for the future waste strategy for Jersey, and any site requirements are used to inform the next review of the Island Plan, 2026 onwards.
MINISTER FOR INFRASTRUCTURE
REPORT Introduction
The La Collette Waste Management Site occupies the reclaimed land within La Collette Reclamation Phase II. The site is the location of the majority of the Island’s solid waste management facilities. Since completion of the reclamation site construction, the La Collette Waste Management Site has evolved as land has been progressively reclaimed, waste management facilities in other locations have reached the end of their service life, and in response to the Island’s changing waste management needs. The development of the site has been in accordance with policy and planning permissions have been sought as the site has developed. An application made for permission to create the ‘La Collette Headland’ through the deposition of hazardous waste in cells has recently been refused. Therefore, the island is without a facility for the management of hazardous waste. Furthermore, permissions for the disposal of inert waste soils at the site will be exceeded in the short term.
The Minister for Infrastructure is proposing a short/medium term plan, as shown on drawing number 22023-100, that will address the immediate issues the Island faces in relation to the management of hazardous waste and inert waste soils. This plan will also provide the necessary time to develop and implement a long-term strategy to deliver on the Government’s solid waste related policy objectives.
Background
The relevant planning history to the reclamation site and in relation to the deposition of waste at the La Collette Waste Management Site is considered as commencing in 1993 when, in the October of that year, permission was granted under application 17742 for the construction of the rock armour revetment (a full breakdown of all related planning applications/approvals can be found in Table 5. In the appendices)
Further planning applications 17742/A and 17742/B enabled filling the reclamation site up to the level of the breakwater for inert waste soils and hazardous waste respectively. Planning application 17742/C allowed landscaped tipping of the North Mound to a height of 10m above the top of the breakwater
On 11th July 2000, the States Assembly approved proposition P.96/2000 and the proposed La Collette Reclamation Site Phase II - Development Framework
This provided the framework for the future development of land at La Collette Reclamation Site Phase II, including the designation of:
- an area of reclaimed land for the purposes of industrial, storage and warehousing use,
- an area of reclaimed land to be used for super-filling and subsequently for the purposes of providing a major landscaped feature and an area of reclaimed land to the south of the tanker berth for the public open space,
- purposes of storing aggregate material imported through St. Helier Harbour as an option pending the outcome of a feasibility study to assess the viability of this use,
- an area of reclaimed land for access to the water at all states of the tide and for associated facilities for marine leisure craft.
One of the key objectives of this framework was based on the rationale that: “Given the difficulties in finding a satisfactory alternative for the future disposal of inert and non-combustible waste materials, it is considered to be in the Island’s best interests to maximise the lifetime of La Collette as a tip site and to incorporate super-filling. This will also enable the creation a landscaped buffer, screening the site from the east, and provide an area of public open space.”
At the time the framework was adopted, ‘Safety Zones’ around the fuel storage facilities had not been conceived (pre Buncefield event - 11th December 2005), with these now used to determine appropriate types of development in proximity to the bulk fuel storage facilities (which fall predominantly in the DPZ, Inner Zone and Middle Zone). As a result, the nature of the public open space (refer point ii.) that the La Collette Headland can provide is restricted, and likely to be limited to:
• A landscaped backdrop
• A coastal walk around the perimeter of La Collette
Recognising Challenges at La Collette – The Island Plan
As early as 2002, the Island Plan recognised that La Collette was filling faster than predicted:
Section 14.28 - The Solid Waste Management Strategy recognises the need to provide additional capacity for waste disposal in Jersey. The Strategy recommends that additional space be created at La Collette through land raising by developing a landform above the sea wall level.
Furthermore, the current Bridging Island Plan recognises that: ‘The Government of Jersey landfill facility at La Collette is, currently, the only licensed terrestrial inert waste disposal site in the island. The facility is reaching the end of its operational life’.
The La Collette Waste Management site
The waste operation at La Collette includes the management of municipal and bulky waste through the Energy Recycling Facility (ERF), the Clinical Waste Incinerator (CWI), Household Recycling Centre (HRC), Metals Recycling Facility (MRF), organic recycling, aggregate recycling, inert waste, and hazardous waste, including asbestos.
The one hectare of remaining land is to be used
for bulky waste storage to enable the ongoing
management of Islanders municipal and bulky waste disposal during the ERF scheduled maintenance periods. This is subject to a future planning application.
With the ongoing high volumes received into the site, issues surround the management of hazardous waste, which is now in breach of its permission condition, and inert waste, which is likely to breach its condition in the short term.
Inert Waste
Inert waste soils are generated through island wide developments. The vast majority of inert waste soils are received at the Inert Waste Soils Reception at the La Collette Waste Management Site, which is one component of the overall inert waste soils and aggregate recycling operation at the site. There are number of small facilities around the island that can receive and recycle inert waste soils. However, the La Collette Waste Management Site is the only facility that has permission for disposal of any surplus non- recyclable content.
Approximately 200,000 tonnes of inert materials are received at La Collette Waste Management site annually. Of this, approximately 120,000 tonnes are recycled into aggregates for use in construction. The surplus 80,000 tonnes are disposed of at the site.
The current planning permissions covering the inert waste soils and aggregate recycling operation permit disposal and landfilling up to the top of the rock armour revetment that forms the perimeter of the site. Stockpiling of soils and aggregates to an average height of 10m and a maximum height of 20m above the top of the revetment is also permitted. The site is currently full and soils and recycled aggregate products are now being stockpiled. At current rates of reception and recycling, it is expected that the permitted stockpiling limits will be exceeded in the short term. This is subject to a future planning application.
Hazardous Waste
Hazardous waste generation is a consequence of essential functions that support Island life. There are three main hazardous waste streams in Jersey:
• Ash and residues from incineration of waste (ERF, CWI, and ACI – Animal Carcass Incinerator)
• Asbestos containing materials (ACMs)
• Contaminated soils
There are other hazardous waste types generated on Island, primarily through industrial activity such as boat cleaning, however, the quantities of these types of waste are relatively small.
The majority of ash and residues come from the ERF and are exported to the UK. This is possible and permitted by the relevant UK authorities as this waste is exported for recovery so is moved up the waste hierarchy by exporting from Jersey. Relatively small quantities of ash and residues arise from the CWI and ACI.
Asbestos containing materials arise from the refurbishment and demolition of buildings, received from homeowners undertaking work on their property and commercial customers and licensed asbestos removal contractors carrying out refurbishment and demolition works for others. Asbestos waste cannot be exported as permission has been refused by the relevant UK authorities.
Contaminated soils are generated through development of contaminated land which exists across the island and are normally the result of historic industrial and commercial operations, for example:
• Old gas works sites & petrol stations
• Scrapyards
• Land reclamation and waste landfilling
• Industrial plant waste storage and treatment facilities
Hazardous waste is disposed of in waste containment cells at the La Collette Waste Management Site. The design, construction and operation of these cells is stringently regulated under the Waste Management (Jersey) Law 2005. The site has a Waste Management Licence issued under this law for the receipt and disposal of hazardous waste. It is a condition of this licence that the design of cells is undertaken by independent specialists and meets the requirements of international standards. The design must be approved by the Waste Regulator prior to construction. Construction of cells is supervised by an independent Construction Quality Assurance (CQA) Engineer. A CQA Validation Report confirming cells have been properly constructed, in accordance with the design, must be sent to the Waste Regulator for approval before the cell can become operational. The waste deposition operation is undertaken in accordance with a Waste Regulator approved Working Plan.
Over the last 10 years, approximately 250,000 tonnes of hazardous waste have been disposed of at La Collette. The producers and sources of this waste is summarised in the following table 1:
Producer |
Ash and residues from waste incineration |
Asbestos containing materials |
Contaminated soils |
Total |
||
ERF |
CWI |
ACI |
||||
Government |
61,900 |
200 |
800 |
500 |
24,300 |
87,700 |
ALO’s |
0 |
0 |
0 |
100 |
145,300 |
145,400 |
Third party |
0 |
0 |
0 |
6,700 |
12,700 |
19,400 |
Total |
61,900 |
200 |
800 |
7,300 |
182,300 |
252,500 |
- All quantities are given in tonnes to the nearest 100 tonnes.
- The majority of the 24,300 tonnes of contaminated soils produced by Government of Jersey was due to the construction of the New Sewage Treatment Works.
- ALO – Arms-Length Organisation
Some significant activities that will generate hazardous waste in the future are listed in the following table 2:
Activity |
Producer |
Hazardous Waste Type |
Quantity (tonnes) |
Animal carcass incineration |
Government |
Ash / Residue |
150 pa |
Clinical waste incineration |
Government |
Ash / Residue |
40 pa |
General asbestos removal |
- |
Asbestos |
730 pa |
New Healthcare Facilities |
Government |
Asbestos / Contaminated Soils |
Unknown |
Tunnel St / Gas Place development |
Government |
Contaminated Soils |
Unknown |
Overdale Hospital works |
Government |
Asbestos / Contaminated Soils |
Unknown |
Southwest St Helier Masterplan |
ALO |
Contaminated Soils |
360,000 |
Elizabeth Harbour redevelopment |
ALO |
Contaminated Soils |
Unknown |
With the exception of the ‘North Mound’ which has specific permission linked to the ERF permission (P17742/C), planning permits for disposal of hazardous waste at the site generally give permission for waste to be filled to the top of the rock armour revetment. Hazardous waste super-filling is already above this with the highest point being approximately 17m above the top of the revetment.
Planning Application – Hazardous Waste
In 2016, planning application P/2016/1647 – ‘Construction of La Collette Headland for super-filling with hazardous waste’ was submitted. The resolution of the planning application has been delayed significantly, and in March 2023, whilst the Planning Officer recommended the application be approved, the Planning Committee chose to refuse the application, siting:
- Policy MW3 – In this instance, insufficient information has been submitted with the application to satisfy the comprehensive after-use restoration plan requirement of the policy,
- Policy GD9 – given the proposed siting, height, scale, and profile of the development proposed, together with a lack of information to demonstrate how this proposal can be satisfactorily mitigated, the development will result in visual harm to the skyline, and
- Policy GD9 – the development given its siting, height, scale, and profile in this location with obstruct significant views to the Noirmont Headland
This is due for formal confirmation of the refusal on the 13th April 2023
The application did include a proposed Landscaping Strategy, Landscaping & Restoration Drawings, Construction Environmental Action Plan, and Working Plan
required under the facility Waste Management Licence which were submitted alongside the application. The Landscape and visual impact was discussed in detail in the application, and an assessment in accordance with recognised standards was undertaken and described in the Environment Impact Assessment. This EIA concluded that the Headland would see no significant impact and instead deliver moderate benefits. It was also felt, as the Headland would provide an essential facility for the Island for which there is no viable alternative, that the overall community benefit outweighs the adverse effects.
The Impacts of Planning Refusal
Given that the La Collette Waste Management Site is already exceeding its permission with regards to hazardous waste, the site will need to close to the receipt of hazardous waste from the 14th April 2023 once the planning refusal is confirmed. This effectively means that the Island will be without a facility or solution for the management of Hazardous Waste.
The result of this means that existing activities generating hazardous materials will need to cease –including:
- Clinical waste and animal carcass incineration
- Asbestos removal and disposal
- Any construction/development on a contaminated site (as listed with Environmental Health or otherwise)
- Boat washings and any other small scale domestic hazardous waste creation. e.g. driveway planings, etc.
For a full list of current/ongoing activities that will need to cease, refer to table 6 in appendices.
Additionally, future developments on contaminated sites (detailed in table 2.) would not be able to progress, with Planning already advising likely refusal of some applications on the basis of the Hazardous Waste decision. Finally, there is a significant increase in the environmental risk of fly-tipping hazardous materials on Jersey.
This is likely to impact all aspects of the Governments’ ability to deliver the seven priorities for change under the common strategic policy. Furthermore, this will significantly hinder the future housing growth strategy as defined in the Bridging Island Plan.
Short/Medium Term Plan
A full options appraisal has been undertaken on the management of hazardous waste (see Appendices, Table 3.), with two options shortlisted (see Appendices, Table 4.) and only one viable option identified:
La Collette Headland – Super-fill La Collette reclamation site as per refused planning application
Given the additional challenge of the inert waste soils also being at risk of breaching its conditions in the near future, it is proposed to address both the hazardous waste and inert soil waste together under a revised ‘La Collette Waste Management Site – Development Plan’. This will form the short/medium term plan.
The ‘La Collette Waste Management Site – Development Plan’ as shown on drawing number 22023-100, is summarised as follows:
• Formation of ‘East Headland’ and ‘South Headland’ by deposition of hazardous waste in cells as per plans submitted under application P/2016/1647
• Formation of the ‘West Headland’ by deposition of inert waste soils in a mound
• Landscaping and restoration of the East Headland and South Headland as per the plans submitted under application P/2016/1647
• Creation of a publicly accessible one-mile-long coastal path around the perimeter of the site
The exact shape, form, and proposed landscaping and restoration of the West Headland will be refined hereafter, and a separate planning application made for its construction. At the current rates of receipt and recycling, the West Headland is expected to be formed in 24 months. The East and South Headlands are estimated to take 5 – 7 years to form. The coastal path will be developed thereafter.
Long Term Strategy
The short/medium term plan will provide the necessary time to complete ongoing work to update the Government’s Solid Waste Strategy and implement any measures this strategy proposes for future waste management. This could include the identification and preparation of new or extended waste management sites around the Island and the development of any infrastructure needed to support these. The strategy will be aimed at achieving the Government’s waste related policy objectives with a focus on prioritising waste reduction, re-use, and recycling as per the waste hierarchy.
Additional Impacts
Should the La Collette Waste Management Site become unavailable for the receipt of hazardous waste materials, then there are two potential options, albeit both carry considerable challenges for the Island.
- Remove hazardous waste at source – Requires the restriction of construction activities that generate hazardous waste, likely the refusal of planning permission on any contaminated area construction. This would have a widespread local impact (construction industry and the Public) in the short term
- Develop an alternative waste site – Requires plans to bring forward rapid construction of an alternative site to facilitate hazardous waste management. This carries a number of environmental challenges, and would not be a quick solution – likely to be 2-3 years minimum
It is also worth noting that there is no option to export hazardous waste given that any Duly Reasoned Request (DRR) to do so would be rejected due to Basel Convention and DEFRA requirements. Furthermore the cost to export hazardous waste would be significant:
Export existing stock to UK: £100,000,000 (approx. 505,000t over last 20 years) Exporting expected Waterfront volumes to UK: £72,000,000 (over next 10-15 years) Normal operational volumes exported to the UK: £50,000,000 (over next 10 years) £200 cost per tonne
Financial and manpower implications
Support for this proposition will not directly influence the financial position the Department will be in should the planning application be refused.
The hazardous waste budget is designed to cover the operational and infrastructure costs and therefore there are no financial implications attributed to this proposition.
Annual budgeted net income for inert waste is £2.3M, with circa £100k of internal manpower resource allocated to the waste management operation for inert waste. Support of this proposition will confirm the States agreement of the Development Plan, which should enable planning permission to be considered in this context, and the continuation of this operation.
APPENDICES Topography & Images
Safety Zones within La Collette Reclamation Site Phase II
Option |
Description |
Advantages |
Disadvantages |
Viability Commentary |
Viable |
Short List |
1 |
La Collette Headland – Super-fill La Collette reclamation site as per refused planning application |
• Site is available and owned by Government of Jersey • Co-location with other GoJ solid waste management functions • Existing infrastructure and operations to support facility • Planning application submitted • Application recommended for approval by Planning Officer • Provides maximum capacity for hazardous waste at La Collette • Accords with historic States Assembly in principle approvals for the management of waste at La Collette |
Planning application refused by Planning Committee |
Other than the refusal of permission by the Planning Committee, which could be contested, there are no other disadvantages |
Yes |
Yes |
2 |
Super-fill La Collette reclamation site to reduced height and super-fill other areas of La Collette |
• Site is owned by Government of Jersey • Co-location with other GoJ solid waste management functions • Existing infrastructure and operations to support facility • Reduced height would address concerns of Planning Committee • Provides maximum capacity for hazardous waste at La Collette • Accords with historic States Assembly in principle approvals for the management of waste at La Collette |
• Site is not available due to current land uses for other waste management functions at La Collette • Other possible visual / environmental impacts due to additional super-fill areas |
Lack of site availability is an obstructive disadvantage |
No |
No |
3 |
Super-fill La Collette reclamation site to a reduced height |
• Site is owned by Government of Jersey • Co-location with other GoJ solid waste management functions • Existing infrastructure and operations to support facility • Reduced height would address concerns of Planning Committee • Accords with historic States Assembly in principle approvals for the management of waste at La Collette |
• Reduced capacity for hazardous waste that is unlikely to support the island’s needs in the medium / long term • Requires additional measures (Option 6) to minimise the generation of hazardous waste in the future that would have significant impact on the public, construction industry and ability to deliver key GoJ policy objectives (e.g. Housing) |
• The concerns of the Planning Committee may be addressed • Would require restriction of activities that generate hazardous waste that would have a widespread local impact in the short term • However, these measures are likely to be required in the long-term whichever solution is adopted |
Yes |
Yes |
Full options appraisal – Table 3.
Option |
Description |
Advantages |
Disadvantages |
Viability Commentary |
Viable |
Short List |
1 |
La Collette Headland – Super-fill La Collette reclamation site as per refused planning application |
• Site is available and owned by Government of Jersey • Co-location with other GoJ solid waste management functions • Existing infrastructure and operations to support facility • Planning application submitted • Application recommended for approval by Planning Officer • Provides maximum capacity for hazardous waste at La Collette • Accords with historic States Assembly in principle approvals for the management of waste at La Collette |
Planning application refused by Planning Committee |
Other than the refusal of permission by the Planning Committee, which could be contested, there are no other disadvantages |
Yes |
Yes |
2 |
Super-fill La Collette reclamation site to reduced height and super-fill other areas of La Collette |
• Site is owned by Government of Jersey • Co-location with other GoJ solid waste management functions • Existing infrastructure and operations to support facility • Reduced height would address concerns of Planning Committee • Provides maximum capacity for hazardous waste at La Collette • Accords with historic States Assembly in principle approvals for the management of waste at La Collette |
• Site is not available due to current land uses for other waste management functions at La Collette • Other possible visual / environmental impacts due to additional super-fill areas |
Lack of site availability is an obstructive disadvantage |
No |
No |
3 |
Super-fill La Collette reclamation site to a reduced height |
• Site is owned by Government of Jersey • Co-location with other GoJ solid waste management functions • Existing infrastructure and operations to support facility • Reduced height would address concerns of Planning Committee • Accords with historic States Assembly in principle approvals for the management of waste at La Collette |
• Reduced capacity for hazardous waste that is unlikely to support the island’s needs in the medium / long term • Requires additional measures (Option 6) to minimise the generation of hazardous waste in the future that would have significant impact on the public, construction industry and ability to deliver key GoJ policy objectives (e.g. Housing) |
• The concerns of the Planning Committee may be addressed • Would require restriction of activities that generate hazardous waste that would have a widespread local impact in the short term • However, these measures are likely to be required in the long-term whichever solution is adopted |
Yes |
Yes |
Full options appraisal – Table 3 (cont.)
Description |
Advantages |
Disadvantages |
Viability Commentary |
Viable |
Short List |
Export hazardous waste |
No local environmental impact |
• Requires permission from relevant authority in receiving country – indication that permission would not be granted • Obstructive costs for export would have significant impact on the public, construction industry and ability to deliver key Government policy objectives (e.g. Housing) |
Inability to secure necessary permissions from relevant authority in receiving country is an obstructive disadvantage |
No |
No |
Disposal on island at another site - either landfill or super-fill |
Possible reduced environmental impact relative to other options |
No site available in Government or third-party ownership |
Lack of site availability is an obstructive disadvantage |
No |
No |
Severely restrict on island activities that generate hazardous waste and work towards ‘Zero Waste’ |
• Accords with Bridging Island Plan Policy WER 1 o Waste Minimisation • Lowest environmental impact relative to other options • Long term solution that must be strived for to support all options |
• ‘Zero Waste’ in the context of hazardous waste in Jersey is not possible in the foreseeable future due to the ongoing existence of sources of hazardous waste • Significant impact on the public, construction industry and ability to deliver key GoJ policy objectives (e.g. Housing) |
Inability to achieve ‘Zero Waste’ in the context of hazardous waste in the short to medium term is an obstructive disadvantage that could only be overcome if Option 1, 2 or 3 was chosen to provide a facility during the period required to implement necessary measures |
No |
No |
2023 P.17
Options appraisal – Short List – Table 4.
Option |
Description |
Public Impact |
Commentary |
Rank |
1 |
La Collette Headland – Super-fill La Collette reclamation site as per refused planning application |
Low |
Impact is limited to a visual impact to a very small volume of the population due to obstruction of views of Noirmont Headland from coastal areas from Grève D’Azzette to Le Squez
This is mitigated to an extent through the landscaping restoration that would be developed along the Headland, masking already visible aspects of the La Collette waste operation |
1 |
2 |
Super-fill La Collette reclamation site to reduced height and super-fill other areas of La Collette |
High |
• Reduced visual impact • However, views of Noirmont Headland from coastal areas from Grève D’Azzette to Le Squez would still be obstructed / compromised • Requires restriction of activities that generate hazardous waste that would have a widespread local impact in the short term or… • …Requirement to bring forward rapid construction of an alternative site to facilitate hazardous waste management |
2 |
THE ONLY VIABLE OPTION IS OPTION 1 – LA COLLETTE HEADLAND Full details of Planning applications/approvals - Table 5.
Date |
Planning Ref. |
Description |
Decision |
October 1993 |
17742 |
Construction of breakwater |
Approved |
January 1995 |
17742/A |
Filling of the reclamation site with inert waste soils up to the level of the top of the breakwater (14m above admiralty chart datum) |
Approved |
September 1995 |
17742/B |
Filling of the reclamation site with hazardous waste in the form of incinerator bottom ash up to the level of the top of the breakwater (14m above admiralty chart datum) |
Approved |
October 1996 |
17742/C |
Landscaped tipping within the area of the ‘North Mound’ to height of 10m above the top of the breakwater (24m above admiralty chart datum) |
Approved |
July 1998 |
17742/D |
Super-filled landscape mound for asbestos disposal |
Withdrawn |
July 2000 |
P.96/2000 |
La Collette Reclamation Site Phase II – Development Framework approved by the States Assembly |
Approved |
November 2015 |
P/2015/1461 |
Construction and filling of Cell 30 with asbestos |
Approved |
November 2016 |
P/2016/1647 |
Construction of La Collette Headland for super-filling with hazardous waste |
Refused (7 years after submission) |
2023 P.17 List of current hazardous waste activities that will need to cease on 14th April should the planning application refusal be formalised - Table 6.
Hazardous Waste Activity |
Dates / Amounts (where known) |
Remediation and likely disposal of materials from warehouse on albert pier |
Requested for April disposal |
Contaminated soil remediation currently in progress |
Presently on site – once remediated disposal. |
Sand Blasting Media with Marine Antifoul |
Various Producers – Requested for April |
Unconfirmed contaminated material Residential Property |
Expected to be requested for April |
Haut Du Mont Incident – Government of Jersey |
Ongoing |
Soil, Insecticide and Mixed contaminants |
Expected to be requested for April |
IHE Operational wastes: Animal Carcass Incinerator Bottom Ash |
Every 6 to 8 weeks |
Clinical Waste Incinerator Bottom Ash |
Every 4 weeks |
STW Gas Stack Scrubber Media |
Quarterly |
Asbestos |
|
The former Play dot com/BOA warehouse/Northern Quarter |
Approx 50 T |
HM Prison La Moye |
Approx 3T |
Midbay Pumping Station works |
Not known |
Various domestic projects, including licensed works |
Not known |
Page - 16
P.17/2023