The official version of this document can be found via the PDF button.
The below content has been automatically generated from the original PDF and some formatting may have been lost, therefore it should not be relied upon to extract citations or propose amendments.
1240/5(3516)
WRITTEN QUESTIONS TO THE MINISTER FOR ECONOMIC DEVELOPMENT BY DEPUTY S.S.P.A. POWER OF ST. BRELADE
ANSWERS TO BE TABLED ON TUESDAY 23rd OCTOBER 2007
Question
- Would the Minister confirm that Jersey Harbours has ordered a newlargemobilecrane for use on theNew NorthQuay to replace the existing fixed tripod craneand, if so, would the Minister informmembers –
- what the lift capacity and reach of the newmobilecrane will beandwhetherthecable drum will have sufficient capacity to load orunload ships at low spring tides?
- w h ether any strengthening or reinforcement will be necessary on the New North Quay to accommodatetheweight and size of this largemachine and, if so –
- what works will be needed andwhat the anticipated costs will be?
- whether the New North Quay will be closed for shipping purposes during the period of any required works?
- when the works will commenceat the NewNorthQuay and what will betheirduration?
- whether the VictoriaQuay will be used for any periodof time to unload ships whileworks are carried out at the New NorthQuay, and, if so,where the existing vessels that moor on the Victoria Quay will be accommodated?
Answer
Jersey Harbours has placed an order for a Liebherr LHM 250 Harbour Mobile Crane, to replace the scotch derrick on the New North Quay. This derrick is in excess of 30 years old.
- The crane has a safeworking load of 64tonnesinheavy lift mode and 44tonnes in normalmode.By comparison the existing scotch derrick has a safeworking load of35tonnes. Part of the design specification included provisionfor the cranetobe fitted with sufficient purchasecable to reach the lower hold of a ship at extreme low water.
- The New North Quay has been surveyed prior to placing the order for the new harbour mobile. No strengthening or reinforcement is required for the existing structure. Theworkingareas of the crane pads will be marked out to coincide with thestrengtheningmembers that support the surface ofthequay.
( i) No strengthening works will be required, although clearing the quay will afford the opportunity to repair
some working surfaces.
( ii ) The New North Quay may have to be closed briefly for the unloading of and erection of the new crane.
A maximum of 2 weeks is envisaged for this purpose.
( ii i) The crane is scheduled to leave the factory on 19th January. The Liebherr Logistics Manager is still
working on a plan for delivery to Jersey. Approximate arrival in Jersey is expected mid February.
( iv ) The Victoria Quay will be used for a period to unload liner service vessels whilst work is carried out on the New North Quay. This is already a working berth for other services and as such is kept available for commercial bookings made. The west cross area will be kept clear during this period. There are no
permanent berths allocated in this area. Vessels moored there are allowed to do so on the understanding that they
must move for operational vessels.
Question
- Would the Minister inform memberswhether the crane that was inadvertently draggedup the VictoriaQuay by the LogosIIis still in a usable state to unload freight?
Answer
During the berthing incident involving Logos II one of the harbour cranes was contacted by the bow and pushed a short distance down the quay. Damage sustained was superficial and repaired within 24 hours. The crane was subsequently inspected and has been in use ever since.
Question
- Would the Minister inform memberswhatimprovements,ifany, have been carried out on the VictoriaQuay to ensure the safe boarding of vessels on that quay, particularly adjacent to that part ofthe quay near the ice- machine?
Answer
There is a half tide ladder provided for boarding vessels on the London Berth. Previously fishermen had attached an unsafe appliance to the bottom of this, which has now been removed. Following consultation with HSI signage has been placed by this ladder giving warning of its limitations. Jersey Harbours is in the process of placing additional pontoons along this berth for use by fishermen. This project is underway now. Access to these pontoons will be via the stems in the corner of the berth.