Skip to main content

Allocated budget and proposed costs relating to the provision of new accommodation for the States of Jersey Police

The official version of this document can be found via the PDF button.

The below content has been automatically generated from the original PDF and some formatting may have been lost, therefore it should not be relied upon to extract citations or propose amendments.

1240/5(7159)

WRITTEN QUESTION TO THE MINISTER FOR TREASURY AND RESOURCES BY DEPUTY J.A. MARTIN OF ST. HELIER

ANSWER TO BE TABLED ON TUESDAY 23rd OCTOBER 2012

Question

Would the Minister provide a detailed analysis of the allocated budget and proposed costs relating to the provision of new accommodation for the States of Jersey Police (this should include the construction of a new Police HQ at Green Street Car Park, together with any other facilities being provided)?

Answer

The project has a budget of £21.07m, which is to be funded through the following allocations:

 

Unspent Project Budget

£19,070,000

Allocation 2013

£1,000,000

Allocation 2014

£1,000,000

Total Funding available:

£21,070,000

The latest cost estimate at December 2011 prices is set out below:

 

Item

Estimated cost

Construction costs (including externals and contingency)

£17,465,315

Professional and other fees

 £2,300,000

Client Fixtures, Fittings and Equipment

 £647,000

Set up of off-site archive & garage

£30,000

Migration

 £25,000

Contribution to Eastern Cycle Track (planning)

£25,000

Total estimated costs @ Dec 2011

£20,492,315

Whilst there is an appropriate sum for contingency within the construction figure, it is important that further provision is made for other client contingency (e.g. design issues) and the effects of inflation on the completion of the project. It is considered prudent to set aside £500,000 for client contingency and the project Quantity Surveyor has advised that a provision for inflation to completion should be £1,150,000.

Including this contingency results in the estimated costs exceeding the allocated budget. In design terms the project is still at an early stage, so after the planning decision the Project Team will tackle any cost issues through detailed design and value engineering, the procurement process and reviewing levels of contingency.

Although not part of the provision of a new Police HQ, in conjunction with our TTS colleagues we will be assessing the provision of car parking in St. Helier .