Town Park breakdown of funds

The official version of this document can be found via the PDF button.

The below content has been automatically generated from the original PDF and some formatting may have been lost, therefore it should not be relied upon to extract citations or propose amendments.

1240/5(6723)

WRITTEN QUESTION TO THE MINISTER FOR TRANSPORT AND TECHNICAL SERVICES BY THE CONNÉTABLE OF ST. HELIER

ANSWER TO BE TABLED ON TUESDAY 21st FEBRUARY 2012

Question

Would the Minister provide a detailed breakdown of how the available funds for the creation of the Millennium Town Park have been spent?

Answer

The  Millennium  Town  Park  project  has  a  budget  of  £11,571,832.94  which  is  a combination  of  £10m  that  was  voted  by  the  States  in  2010  and  the  remainder (£1,571,832.94) which was transferred from Property Holdings who previously held the planning  vote  for  the  project  before  it  was  transferred  to  Transport  and  Technical Services.

The new Millennium Town Park opened at the end of October 2011 with some small remaining items being completed by December 2011. Transport and Technical Services are currently working with the Park contractor to settle the final account for the project. It is not unusual for a complex account of this nature to take six months to finalise and as such, the figures listed below are the current best estimates which may alter when the final account is settled.

The total costs for the project will not exceed the available budget.

Millennium Town Park - Cost Breakdown Summary

Item  Cost (£)

1  Feasibility and investigation of below ground contamination from

previous gas making activities  £1,197,321 2  Professional fees for remediation, planning, design and

construction  £1,994,827 3  Contaminated land, remediation and engineering works  £2,374,777 4  Utility Building (includes public toilets, disabled toilets, first

"Changing Places" facility on the Island, baby changing facilities,

store room for the "Friends of the Park", JEC substation,

mechanical and electrical switch room, mess facilities and

materials and equipment storage for the Park staff)  £640,329

5  Mechanical, electrical, water infrastructure  £773,616 6  Paving  £1,379,097 7  Planting  £857,237 8  Play area  £208,520 9  Practice court and petanque area  £115,967 10  Park furniture and pergolas  £259,805 11  Water curtain  £261,011 12  Water field  £287,230 13  Public art  £78,046 14  Railings, gates and plinths  £541,491

Resurfacing of adjacent Parish roads – TTS agreed with POSH to undertake as much of this work as possible within funds

 remaining after main project was complete

15  Supply of granite for total of adjacent road improvements  £374,557 16  Lay only of part of adjacent road improvements (POSH to

complete the remaining)  £228,002

Total Cost  £11,571,833

The original capital allocation for the Millennium Town Park included an additional £0.5M for a separate capital project which has now been returned to Treasury and is not included in the figures above.