WQ.235/2022
WRITTEN QUESTION TO
THE MINISTER FOR ECONOMIC DEVELOPMENT, TOURISM, SPORT AND CULTURE
BY THE CONNÉTABLE OF GROUVILLE
QUESTION SUBMITTED ON MONDAY 24th OCTOBER 2022
ANSWER TO BE TABLED ON MONDAY 31st OCTOBER 2022
Question
Given that the draft Government Plan 2023-2026 includes £11.7 million of funding allocated to the Jersey Opera House, will the Minister provide –
- a detailed breakdown of the schedule of works to be carried out based on this figure, together with the proposed timeframe of each itemised piece of work; and
- a schedule of all proposed on-going maintenance on completion of the above works, detailing the future funding provision to ensure annual maintenance rather than periodic high repair costs?
Answer
A detailed breakdown of the scope of works for the renovation project is included in the below annex.
Following the allocation in the proposed Government plan of £11.7m towards the renovation of the Jersey Opera House we have now assembled a project Board to oversee the delivery of this important renovation project.
The project Board is chaired by a senior officer from the Economy Department and also includes representatives from Jersey Property Holdings and the project management firm who are to deliver the renovation works.
I have asked this project Board to provide me with a detailed project timeline against the scope of works by the end of the year.
We are currently working on a new legal structure operating model for the Jersey Opera House company. Within this operating model we will factor in a fully costed maintenance fund to ensure that the pressure of maintaining the building is removed from those in charge of the arts programme.
Annex
GROUND FLOOR INTERNALS
1 Auditorium, Foyer & Corridors Replace auditorium and front of house carpeting
- Auditorium Remove, reupholster and refix auditorium seats
- Auditorium MEP Clean duct under auditorium seating
3 Auditorium DDA Adapt row G seats to make easily removeable
- Auditorium DDA Change seat designs/adapt for DDA
- Auditorium MEP Move and reinstate sound desk
5 Auditorium DDA Adapt seats
- Stage repoint part of granite, rigging edge protection, repaint floor
- Stage MEP Remove and refix MEP equipment
- Stage check stage fire curtain, input required Fire Consultant
- Stage MEP JF&R report required to check if existing drencher compliant
- Circulation areas/ramps DDA colours, add signage, handrails, replace doors with vision panels
- Circulation areas/ramps MEP emergency lighting in connection
9 Berni suite make good water ingress to external walls , redecorate
- Berni suite DDA adapt bar to create lower portion of counter
- Berni suite MEP Remove, refix and adapt MEP equipment
- Male WC replace 3 nr damaged urinals IPS system
- Male WC MEP replace above with cisternmiser and pipework modifications
- Corridor relocate fire doors to ramp
- Corridor MEP Upgrade emergency lighting, alarms etc, electromagnetic door hold open
- Lower Stalls Bar concrete repairs to studio soffit above
- Lower Stalls Bar MEP remove and refix MEP installations for above
14 Lower Stall Bar DDA redecorate contrasting columns
- Lower Stalls Bar / Box Office Counter DDA adapt bar to create lower portion of counter, increase space
- Lower Stalls Bar / Box Office Counter MEP in connection with above
16 Lower Stalls Bar / Box DDA repeat decal
17 Stage Dock replace faulty full height stage door for fire rated door, reuse track
- Laundry / Ward robe Service Room DDA swap washer/drier position, change sink
- Laundry / Ward robe Service Room MEP in connection with above
- Review Stage Loadings survey and report required
- Review Stage Loadings MEP remove and refix to enable above
- Basement Orchestra Pit repair concrete degradation and tanking
- Basement Orchestra Pit MEP remove and refix MEP equipment re above
- Basement Orchestra Pit install pit pumps
- Basement Orchestra Pit MEP pumps (specialist work)
- Basement Orchestra Pit DDA stair lift (previously removed) and screed
- Basement Orchestra Pit MEP stair lift
- Scenery Dock install platform lift (see below), adapt existing stair location etc
- Scenery Dock MEP lift
24 Basement make good fire stopping to stage door DB13 and generally
FIRST FLOOR INTERNALS
- Circle OH! Bar structural concrete soffit repairs, reinstate ceilings
- Circle OH! Bar MEP remove and refix equipment in connection with above
26 Circle OH! Bar DDA add hazard warning/manifestation to glazed balustrading
27 Circle OH! Bar / Foyer DDA decals to mirrors
28 Replace external glazed canopy to circle foyer
29 Circle foyer improve heating and new ventilation system
30 Dressing Room 3 / Green Room MEP no electrics reinstate power
31 Dressing Room 3 / Green Room MEP no ventilation only extract provide new mechanical ventilation
- Dressing Room 3 / Green Room new toilet and shower
- Dressing Room 3 / Green Room MEP sanitary, supplies, wastes etc to above item
33 Chorus Dressing Room make good water damage from roof
34 Chorus Dressing Room MEP replace smoke detectors/review extract ventilation
SECOND FLOOR INTERNALS
35 Dressing Room 4 Riser MEP fire stopping to ducts through compartments
- Dressing Room 4 Riser review lightning conductor and water ingress from roof
- Dressing Room 4 Riser MEP remove and refix to allow remedials to above
37 Dressing Room 4 make good stone wall/boxing due to water ingress
- Dressing Room 4 / Disabled WC DDA replace sanitaryware and vinyl
- Dressing Room 4 / Disabled WC MEP incl install secondary lower level shower head
- Green Room Kitchen / Old Living DDA lower part of kitchen counter
- Green Room Kitchen / Old Living MEP refix MEP equipment to enable above
40 Green Room Kitchen / Old Living
41 Studio MEP repair ductwork and services
- Studio repair roof following water ingress
- Studio MEP remove and refix MEP to enable above
43 Studio superficial repairs to protective floor matting to sprung floor
44 Studio DDA decals to mirrors at knee height
45 Rehearsal Room DDA decals to mirrors at knee height
46 Rehearsal Room Make good decorations following water ingress
THIRD FLOOR INTERNALS
47 Plant room new tanking membrane, hazard demarcation
48 Plant room MEP only one pump working; replace 8 pump heads
49 Plant room make good internals following water ingress
50 Plant room review blockwork/fire stopping to wall to riser cupboard
51 Plant room Roof Health & Safety, exposed insulation over joists, investigate decking over 52 Plant room remediate damp issues/rot to timbers
53 Chandelier / Dome investigate and add new structural ring beam supports
- Chandelier / Dome remove ply flooring to inspect structure (levels dip)
- Chandelier / Dome MEP remove & refix MEP equipment to enable above
55 Chandelier / Dome permanent handrail supports to dome enclosure
56 Third Floor / Upper Circle Bar make good water ingress to roof over electrical corridor 57 Third Floor Escape Staircase, make good internal walls due to water ingress
EXTERNALS
58 Gloucester Street Elevations repair cracks to painted render walls
59 Gloucester Street Canopy repair cracks to underside of canopy soffit
60 Gloucester Street Elevations repair cracks to painted render walls
- Gloucester Street Foyer Entrance Doors DDA replace defective external refuge point; signage
- Gloucester Street Foyer Entrance Doors DDA MEP (incl doorbell not working)
- Gloucester Street Foyer Entrance Doors DDA, make good
- Gloucester Street Foyer Entrance Doors DDA MEP automatic door openers/closers
- Gloucester Street Box Office Doors DDA, new doors to alternative access, handrails, signage
- Gloucester Street Box Office Doors MEP push pad door automation to 1 nr double doors
64 Gloucester Street External Lightning MEP replace uplighters
65 Gloucester Street remove rusted fixings, make good render, redecorate
66 Gloucester Street Canopy
67 Gloucester Street scaffold, further inspections, repair, redecorate
- External Windows make good panes, beads and single glazing, redecorate
- External Windows
69 First & Second Floor Glazing Gloucester Street elevation, replace rusting frames, new safety glass 70 Fourth Floor repair cracks to render/parapet wall
71 Second Floor Studio & Office Roofs, make good, possible new insulation
72 Second Floor leanto slate roof (over Rehearsal Studio) Investigate and repair valley
73 External Seaton Place façade, repair cracking and redecorate
74 Provide new edge protection to roof to improve roof access, plus rooflight guards
75 Existing emergency escape door (West elevation Gloucester Street), damp remedials, new ACO 76 External Car Parking lines DDA liaise with Parish for designated disabled drop off/pick up
77 External Signage DDA Patriotic Street car park sign indicating shortest route
78 External Seating DDA tipup perching seats
GENERAL ITEMS
79 Fire Doors, replace all existing, add intumescent strips
80 Doors DDA adjust resistance, change handles throughout, signage, contrasting colours
- Front Public Passenger Lift remove existing stairlift, make good walls, localised redecoration
- Front Public Passenger Lift MEP
- Front Public Passenger Lift DDA extend shaft up to third floor, remove stair lift, make good
- Front Public Passenger Lift DDA MEP, extend existing travel, adapt car
- Rear Stage Passenger Lift replacement DDA, builders work
- Rear Stage Passenger Lift replacement DDA MEP
84 Circulation Doors, adjust door closers to reduce resistance
85 Circulation Lobbies/Corridors Signage DDA update throughout, replace missing hooks etc
86 Bars & Box Office Counters DDA replacement laminates, spray rails
- Disabled Accessible Toilets DDA replace back panels, handrails, vinyl flooring, adjust fittings heights
- Disabled Accessible Toilets MEP
88 Acoustic Booth DDA MEP
89 Rooftop Handrails, low level parapet upstands only
90 Asbestos Report
OTHER MEP ITEMS
91 Clean/update/refurb HVAC to all areas
92 Supply and extract ventilation to back of house & under stage 93 Replace Dx system serving Opera House AHU plant
94 Replace Dx system serving common areas
95 End of life boiler replacement
96 Make radiators LST
97 Update Trend control systems
98 Clean LTHW heating system
99 Replace water services pipework
104 Remove and replace water tank to accessible roof area
105 Legionella works to some water services pipework
106 Replace broken extract fans
107 Replace broken disabled access alarms DDA
108 Replace lighting control system
109 Replace lighting which is broken or not standard
110 Replace electrical cables
111 Replace electrical switchgear
112 Enlarge incoming JEC supply to suit Gas boiler replacement
113 Remedial works to power following electrical testing
114 Provide power/containment/data to suit new AV/stage systems
115 Replace door security
116 Replace stage sliding door motors
117 Replace studio lamps
118 Fire stopping in connection with MEP services
119 Box Office / Stalls Bar DDA induction loops front of house and dressing rooms 120 External Stage Door / Seaton Place replace intercom
121 Lighting replace throughout with LED, reduce switch heights
122 Auditorium Dress Circle create fire refuge point
123 Auditorium Upper Circle create fire refuge point
124 Laundry / Ward robe Service Room replace ventilation system
125 Switches and sockets DDA contrasting plates
126 Studio DDA extra lighting
127 Back of House risers add collars and dampers
128 Clean all drainage traps
129 Provide dehumidifier to piano store
130 Supply & extract ventilation system under stage for H&S compliance
131 Works to caretakers flat (to be surveyed)
132 Perimeter heating in glass dining area & first floor foyer replace
133 Replace curtain drenching system behind stage
134 Remove and reinstate roof plant above studio
135 Remedial works to existing fire alarm system
OTHER ITEMS NOT ON ARCHITECT'S INITIAL SCHEDULE
136 Redecorate auditorium allowance
137 Survey and Report for fire compartmentation
139 DDA original scope provisional sum
140 Basement floor various including finishes (amber) and door upgrades (red) total £14,687 141 Ground floor various including finishes (amber) and door upgrades (red) total £64,247 142 First floor various including finishes (amber) and door upgrades (red) total £25,056
143 Second floor various including finishes (amber) and door upgrades (red) total £40,231 144 Third floor various including door upgrades, cracks, roof repairs (red) total £20,504
145 Stairwells various including finishes (amber) total £3,075
146 MEP original scope lighting items 109 and 135
147 Provisional sum increased allowance for wall and roof repairs since 2019 survey