Transport and Technical Services Department Ministerial Decision
Decision Reference: Green Waste Composting – Outcome of Stage 1 and Stage 2 Site Assessment | |||
Decision Summary Title (File Name): | MD-T-2007-0113 | Date of Decision Summary: | 11 December 2007 |
Decision Summary Author: | Will Gardiner (Director of Waste Strategy Projects) | Decision Summary: Public or Exempt? | Public |
Type of Report: Oral or Written? | Written | Person Giving Oral Report: | - |
Written Report Title (File Name): | Green Waste Composting – Stage 1 Sites Assessment Green Waste Composting – Stage 2 Sites Assessment | Date of Written Reports: | 11 December 2007 |
Written Report Author: | Will Gardiner (Director of Waste Strategy Projects) | Written Report : Public or Exempt? | Public |
Subject: The site selection and evaluation process for development of new green waste composting sites. | |||
Decision(s): The Minister for Transport and Technical Services is recommended to:
| |||
Reason(s) for Decision: To progress the identification of green waste composting sites in order to implement commitments within the Solid Waste Strategy. | |||
Resource Implications: A capital allocation of £4.212 Million was awarded to the Department in 2006 for development of a replacement (enclosed) in-vessel composting facility. Following the award, the Minister agreed to await the outcome of the Working Party into Composting and then the outcome of the full site |
evaluation process on potential private and States-owned sites before progressing the development of a replacement facility. The delay in implementing this project means that the available budget may no longer be sufficient for all available process technologies, but it is still thought possible to develop a suitable enclosed facility within the funding allocated. The States Business Plan 2008 - 2012 includes £1.452 Million for the development of a permanent Re-use and Recycling facility in 2010. The Solid Waste Strategy envisaged the advantages of combining green waste collection with the permanent Re-use and Recycling Centre and this budget will be used to deliver a permanent combined green waste and Re-use and Recycling Centre facility to that timescale. Capital and revenue and funding for the operation of a second facility to minimise transport of green waste by the public around the island has not yet been identified. However, it may be that the introduction of an Environmental Tax in 2009 would facilitate the operation of a second site and the available budget may be sufficient for two sites to be developed subject to the third stage of detailed financial assessment. The outcome of a risk assessment into the possibility of a Vapour Cloud Explosion at the fuel farm at La Collette has precluded the use of that site for public green waste collection facilities in future. A temporary public green waste collection site has therefore been sought and, following a review of potential sites, the recommended site is Compound 6 within Field 1491 in Bellozanne Valley. This site has the advantages of requiring limited capital investment to become operational. It is estimated that approximately £56,000 of civil works will be required and twelve custom-made collection containers purchased. It is requested that a total of £100,000 be earmarked from the existing Temporary Re-use and Recycling Centre capital allocation for the works. The revenue implications of approximately £113,400 for three extra staff and £12,339 leasing costs of vehicles required to operate this site will have to be met from mid 2008 from existing Transport Technical Services budgets. | |
Action required: The Director of Waste Strategy Projects is to:
| |