Skip to main content

Cyber security arrangements (R.71 /2022): Executive Response

This content has been automatically generated from the original PDF and some formatting may have been lost. Let us know if you find any major problems.

Text in this format is not official and should not be relied upon to extract citations or propose amendments. Please see the PDF for the official version of the document.

STATES OF JERSEY

CYBER SECURITY ARRANGEMENTS (R.71 /2022): EXECUTIVE RESPONSE

Presented to the States on 15th August 2022 by the Public Accounts Committee

STATES GREFFE

2022  R.71 Res.

FOREWORD

In accordance with paragraphs 64-66 of the Code of Practice for engagement between Scrutiny Panels and the Public Accounts Committee' and the Executive', (as derived from  the  Proceedings  Code  of  Practice)  the  Public  Accounts  Committee  (the Committee')  presents  the  Executive  Response  to  the  Comptroller  and  Auditor General's Report entitled: Cyber Security Arrangements (R.71/2022 presented to the States on 6th May 2022).

It is intended for the Committee to be fully constituted after the appointment of Lay Members during the States sitting on 13th September 2022. As such, the Committee will review the responses in detail after its formation and present any further comments to the States Assembly in due course.

Deputy L. Feltham

Chair, Public Accounts Committee

SUMMARY OF RESPONSE

The report on the Cyber Security Programme was published before the final evidence items were provided to the C&AG. As such a number of the recommendations, as they would apply specifically to the Cyber Security Programme, were dealt with through that final exchange of evidence. Many of the recommendations refer to Major Programmes in general and not specifically to the Cyber Programme. Where the recommendation refers to Major Programmes, the response has been provided by the Corporate Portfolio Management Office (CPMO) and/or Strategic Finance. Where the recommendation relates specifically to the Cyber Security Programme, the response has been provided by the Cyber Security Programme, Programme Management Office.

A significant number of the Major Programme recommendations are dealt with through the CPMO Programme Delivery Framework and/or Project Delivery Framework which were published in 2021. At the time that the Frameworks were published, it was agreed that  in  flight  Programmes  and  Projects  would  not  be  required  to  complete documentation retrospectively but would fall into line with the Framework at the next Stage Gate. As such, at the time of the audit, the Cyber Security Programme may not have been fully compliant with the relevant Framework but would be expected to become fully compliant at the next Stage Gate. This situation would apply to all Programmes and Projects that were in flight in 2021.

ACTION PLAN

 

Recommendations

Action

Target Date

Responsible Officer

R1  Secure  documented formal senior approval of any changes to high-level programme targets.

Accepted

This has already been enacted as part of  the  discussion  around  FY22 changes to scope and planning, with Formal CRN-062 being presented to the ACM for review/approval.

Complete

Programme Manager, Cyber Security Programme

R2  For  major programmes,  adopt  a  set of  success  measures  that can be used to evaluate the impact of a programme in a clear and straightforward way.

Partially Accepted

The definition of success measures for programmes and projects are required to  be  set  out  and  approved  in  the business case.  The business case also presents  the  options  identified  and appraised and should clearly articulate the  reasons  for  the  recommended option.   All business cases requiring additional funding are submitted for investment appraisal prior to being recommended  for  approval  via  the

Q3 2023

Head  of CPMO

 

Recommendations

Action

Target Date

Responsible Officer

 

Government  Plan  or  Ministerial Decision. If a business case is approved, the programme/project can move into delivery. The strength of the business case  and  identified  success  measures will determine the ability to effectively evaluate the impact of the programme.

In  2021,  the  CPMO  launched  two Frameworks, the Programme Delivery Framework  and  the  Project  Delivery Framework.  The  purpose  of  these Frameworks is to provide consistency of  language  and  approach  to programme and project delivery and to provide additional control using stage gates. The stage gates mandate formal evaluation  of  the  programme/project against  its  business  case  to  assess whether it is still viable, still represents value for money and is still likely to deliver  the  benefits  defined  in  the business case. This would include any measurable  benefits  identified  in  the business  case  although  it  should  be noted that not all business cases have included measurable benefits. It is the ambition  of  Strategic  Finance  to improve the quality of business cases, which  would  include  a  focus  on including  measurable  benefits.  In addition  to  the  stage  gates,  monthly progress  and  performance  status reporting  on  all  programmes  and projects has been mandated and at the completion of a programme/project, the Frameworks  mandate  a  post implementation  review  and  Closure Report  which  contains  a  clear requirement  for  the  stipulation  of benefits  realisation  plans  and ownership,  should  the  realisation  of benefits  be  in  the  period  post completion of the programme/project.

 

 

 

Recommendations

Action

Target Date

Responsible Officer

 

Going forward all projects initiated (and those defined and planned as part of Government Plan 2023) will follow

the frameworks allowing for the upfront definition  of  success  measures  for consistent  evaluation  throughout. Existing Major projects, particularly those  in  delivery  stages  are  not expected to retrospectively complete documentation and so this process is expected to take until mid to late next year to embed.

 

 

R3  For  major programmes,  set  overall milestones for delivery at programme  level  and monitor  against  those milestones.

Partially Accepted

The  CPMO  frameworks  referenced above provide a standard set of stage gates  throughout  the programme/project  lifecycle.  The stage gates mandate formal evaluation of the programme/project against its business case to assess whether it is still viable, still represents value for money and is still likely to deliver the benefits defined in the business case. In  addition,  monthly  progress  and performance  status  reporting  on  all programmes  and  projects  requires monthly  review  and  updates  to programme/project  milestones.  In 2022, this has been expanded to also require a status against each milestone and  forecast  milestones  to  allow forward planning at a portfolio level.

It is recognised that, as with R2 above, this process will take time to embed. In flight projects are not expected to retrospectively  complete documentation but they are expected to  complete  updates  to  stage  gate milestones via the reporting system on a go-forward basis. Assessment of the validity  of  this  information  is  also required  and  this  will  take  place monthly as part of quality checking on Major and Strategic projects.

Q2 2023

Head  of CPMO

 

Recommendations

Action

Target Date

Responsible Officer

R4 For those workstreams and  projects  where  the focus  is  on  consultancy rather  than  technology implementation,  set milestones for delivery and   monitor  delivery against those milestones.

Partially Accepted

In 2022, all projects, regardless of their

focus, require the definition, monthly

review and update of milestones via

the project reporting tool (Perform). At a minimum these milestones  will

include  the  stage  gates  a  project

will  progress  through.  At  the

completion of a stage gate, the Project

or  Programme  board  is  required  to

approve  any  change  to  milestones

formally prior to the transition to the

next stage.

Work is ongoing to ensure milestones are consistently defined and reported upon via the project reporting tool (See R3 above)

Q2 2023

Head  of CPMO

R5  Undertake  a  formal documented  risk assessment before agreeing deferrals  or  changes  to project deliverables.

Accepted

Formal CRNs for high level decision making on the programme have been in  place  since  the  outset  of  the programme and within the template, there is a section on impact analysis which  includes  provision  for  time, cost, risk, resources, communications and  benefits  in  line  with  standard industry practice.

This has been enacted in the recent CRN-062 which addresses the recent intent to amend the scope and intent for the programme in FY22/23.

Complete

Programme Manager, Cyber Security Programme

R6 Formally document all deferrals  and  changes  to project deliverables.

Accepted

Deferral activity in the detailed sense is  captured  within  the  requirements validation process that is carried out with all packages as they pass through delivery  on  the  Cyber  Security Programme.  We will review specific areas  of  the  Tranche  1  projects  to determine  if  there  are  any  gaps  or timing issues with the validation work

Complete

Programme Manager, Cyber Security Programme

 

Recommendations

Action

Target Date

Responsible Officer

 

that  was  presented  at  the  time  of interview, but it is perceived that no additional  changes  to  process  or approach is required.

 

 

R7 Formally document at a programme level where deferrals  and  descoping have  been  referred  to Ministerial level.

Accepted

The use of formal CRNs for high level decision  making  on  the  Cyber Security  Programme  has  been adopted and in relation to the recent CRN-062, presentation and discussion at ministerial level has been carried out and documented.

Complete

Programme Manager, Cyber Security Programme

R8  Make  best  use  of scarce  internal  staff resources  in  future technology programmes through:

confirming availability during the planning phase; and

engaging with other programme leads to identify activities in common.

Partially Accepted

M&D do their utmost to make best use of scare resource in a fluid, dynamic and complex environment. In the last year, M&D have developed demand management  processes  to  collate, assess and manage the demand arising for  technology  change  and  support from departments, and tracks between 300 and 400 initiatives at any point in time.  This is a reactive rather than a proactive planning approach which is time  consuming  and  results  in resource  forecasting  conflicts.  To address this, there is a requirement to proactively plan (wherever possible),

and this requires a change to the way in which strategic planning takes place. For  the  Government  Plan  and Departmental  Business  Planning 2023,  M&D  and  other  enabling functions  will  be  engaged  in  the planning  process  at  the  outset avoiding unforeseen resource demand and allowing a proactive and joined up  approach  to  planning  and  the assessment of deliverability.

However,  this  alone  is  unlikely  to resolve  the  issue  of  resource availability as plans change often on projects and these resources are also required to maintain the day-to-day

Complete

Group Director, Modern- isation & Digital

 

Recommendations

Action

Target Date

Responsible Officer

 

technology  requirements  for  a complex  organisation  which  often requires a reallocation of resource at short notice. Should the GoJ wish to establish  dedicated  technology resource  teams  for  the  purposes of change,  forward  resource  planning would be more achievable. However, this would come at considerable cost to the organisation and would require significant effort to implement and embed and is therefore not proposed at this stage.

 

 

R9  In  planning  future technology  programmes, assess  the  risks  and opportunities  associated with  simultaneous delivery  of  multiple programmes.

Accepted

As noted above, historically, planning processes  have  not  assessed  the cumulative  viability  of  change  nor have they consistently and formally engaged  with  M&D  to  assess  the individual viability of proposals.

In 2022, as part of the Government Plan 2023  processes,  there  will  be  an assessment of deliverability involving the enabling functions to plan for and schedule  concurrent  delivery.  New processes  in  M&D  such  as  the Architecture Review Board, allow for the identification of technology risks and  opportunities  associated  with concurrent  delivery.  There  is  also ongoing work to ensure the planning processes in T&E are integrated with those  in  the  enabling  functions  to assess  the  appropriate  funding  and planning  of  both  management  and technical  resources  to  enable significant  simultaneous  delivery across the entire portfolio.

Complete

Group Director, Modernisatio n & Digital

R10  Deliver  structured training to risk owners to develop  their understanding  of  and confidence in their role.

Partially Accepted

In  2021,  Espresso  sessions  to introduce  risk  owners  to  the Enterprise Risk Management (ERM) process and tool were implemented. Departmental focused training is also undertaken  where  the  need  is

Complete

Head  of CPMO

 

Recommendations

Action

Target Date

Responsible Officer

 

identified.  Details of  risk  webinars are shared with risk owners and risk groups.

Risk  guidance  setting  out  the difference  routes  for  recording  and reporting  Project/Programme  Risk, Departmental  Risk  and  Corporate Risk has been published.

In  Q3,  the  CPMO  will  introduce quarterly departmental portfolio risk reviews which will focus solely on the programme/project  risk  in  the department  and  whether  there  are suitable mitigations in place.

[NB In the future, Corporate Risk plan to develop a formalised programme of risk  training,  in  terms  of  a  fully structured  competency  framework based training programme for general risk management. Corporate Risk are awaiting  the  outcome  of  a  C&AG review of the ERM prior to embarking on a piece of work which will look at gap analysis around the competency framework and then tailor and cost accordingly.  This is likely to be  a blend of e-learning with compulsory modules  for  all  staff  via  Virtual College  and  more  specific  risk training directed at the different tiers. It is possible Corporate Risk will be recommending departments to follow a similar approach in respect of the latter to that which has been taken with IOSH Managing and Directing Safely but from a CIRM perspective. This includes training at Board level. It is therefore too early to give costing until this work is done.

 

 

 

Recommendations

Action

Target Date

Responsible Officer

 

This  will  be  supplemented  with Expresso  sessions  on  ERM  system navigation,  workshops  on  the framework and specific elements of the  Strategy,  etc.  Some  of  this  is already  being  done  within  existing resource.]

 

 

R11  Develop  formal mechanisms  for  co- ordination  between programmes regarding the prioritisation  and  co- ordination of tasks.

Accepted

As  noted  above,  revisions  to  the Government Plan and Departmental Business  Planning  will  ensure  that M&D and other enabling functions are engaged in the planning process at the outset  and  prior  to  business  case approval,  allowing  a  proactive  and joined up approach to planning and the assessment  of  deliverability. Ministerial support will be necessary to  this  process  particularly  with respect to the prioritisation of projects enabling the project teams to schedule effectively and avoid conflicts.

Complete

Head  of CPMO

R12  Designate  internal owners  for  each workstream  in  major programmes.

Accepted

The CPMO Governance Framework mandates  a  minimum  governance structure  which  includes  a Programme SRO, Senior User, Senior Supplier and PM/PMO. The approach to the programme will determine the roles  beneath  this  structure.  For example,  some  programmes  will define  distinct  projects  beneath.  In such cases, these projects are expected to  also  follow  the  minimum governance structure, putting in place a project level SRO.  In other cases, the  programme  may  decide  to  use tranches or workstreams rather than separate  projects  to  consolidate deliverables. In such cases, a lead for the  tranche or  workstream  must  be agreed  with  the  Programme  board before  the  end  of  the  Define  the Programme'  stage  gate.  The Programme  Framework  which  sets

Complete

Head  of CPMO

 

Recommendations

Action

Target Date

Responsible Officer

 

out such requirements was launched in November 2021, and it was agreed that any inflight programmes (such as Cyber Security) would not be required to  retrospectively  complete documentation. Going forward, these structures  will  be  defined  and reviewed  by  the  Programme  Board and the CPMO prior to progressing to the  next  stage.  As  in  flight programmes  progress  through  their next stage gate, they be required to align  with  the  CPMO  Governance Framework.

 

 

R13  Identify  individuals to deputise as alternates at key programme meetings when  designated individuals  are  not available.

Partially Accepted

The standard terms of reference for Project  Boards  and  Committees requires the identification of named delegates and the clarification of the required quorum. However, given the nature and size of the Government of Jersey,  a  delegate  with  the appropriate  decision-making authority  may  not  always  be  in available.

Complete

Head  of CPMO

R14 In  Outline Business Cases document linkages to  wider organisational strategies and initiatives.

Accepted

The  Investment  Appraisal  Team  is committed  to  supporting  the organisation  in  continuously improving  the  quality  of  business cases produced.

It  has  produced  updated  Business Case  templates,  and  rolled  out  a training programme, guidance, online learning and a resource hub to support business cases authors.

The updated Business Case templates include  a  requirement  to  link  the initiative  to  a  CSP  or  Ongoing initiative.  In  addition,  the  case  for change also specifically asks authors to consider "connections to existing government policies and strategies."

Complete

Group Director, Strategic Finance

 

Recommendations

Action

Target Date

Responsible Officer

 

Impacts  on  other  departments  are specifically required to be assessed, which  would  include  dependencies and linkages to other initiatives.

We  therefore  consider  that  the Business  Case  framework  in  place meets this recommendation, although the actual realisation will depend on the  detail  and  quality  of  each individual business case drafted. The IAT  will  continue  to  support  the organisation in developing the quality of Business Case writing.

 

 

R15  Ensure  that  all workstream  planning activities  in  major programmes  are  fully documented.

Accepted

All Major programmes are required to follow  the  CPMO  Programme Delivery Framework which sets out the  required  documentation  for  the programme.  This  includes  the minimum  standards  for  Programme Plans.

Complete

Head  of CPMO

R16  Routinely  hold workshops  with programme  stakeholders to  identify  and  prioritise requirements for major

programmes.

Partially Accepted

All Major programmes are required to follow  the  CPMO  Programme Delivery Framework which sets out the required documentation for the programme.  This  includes  a stakeholder map and communications strategy to indicate the plan for the management,  engagement  and communication with stakeholders. At the  end  of  each  stage  gate,  the Programme Manager and SRO must confirm they have satisfied the criteria to  enter  the  next  stage  gate  which includes  the  engagement  of stakeholders, clarification of their role in the programme and their approval of prioritised requirements and design. This  document  is  approved  by  the Programme Board and reviewed for completeness by the CPMO.

Complete

Head  of CPMO

 

Recommendations

Action

Target Date

Responsible Officer

R17 Develop and roll out appropriate  induction training  for  external project managers.

Accepted

A  Project  Management  e-learning module  was  launched  in  February 2021 to provide induction training to all new Project Managers to the GoJ, including  any  external  Project Managers.  The  e-learning  includes guidance  on  the  use  of  the  GoJ Programme and Project Frameworks. In addition, training is offered to all new Project Managers (both internal and external) on the use of the project reporting system, Perform.

[NB The Cyber Programme does run familiarisation  sessions  for  new suppliers joining the Cyber Security Programme and within the extended content  we  have  focus  sections  on PMO and Business Change.  This is currently being revised and will be updated in line with the intent to adopt the new CPMO delivery framework etc.  for  FY22  projects  where appropriate/mandated.]

Complete

Head  of CPMO

R18  Introduce

structured  briefings  for stakeholders  at  the commencement  of  their involvement  in  a programme  so  that  they have a clear understanding of their role.

Accepted

This is in place.  See R16.

Complete

Head  of CPMO

R19  For  major programmes,  routinely evaluate  benefits realised and delivery

of  Outline  Business Case  tasks  at programme level.

Accepted See R3 above.

Complete

Head  of CPMO

RECOMMENDATIONS NOT ACCEPTED

 

Recommendations

Reason for Rejection

None