Residential land availability

January 2011

R.119/2011

Preface

The purpose of this report is to provide more up-to-date knowledge on housing supply, to allow comparisons with identified requirements for new homes in the Island Plan, and to assist in ensuring that an adequate supply of suitable housing will be available to meet the community's needs.

It is the intention to provide regular monitoring reports on housing land availability and the performance of related planning policies over the Plan period of the 2011 Island Plan.

Policy and Projects Team, Department of the Environment September 2011

Contents

Page No.

  1. Introduction  1
  2. Summary of findings  1
  3. Future considerations  1
  4. Recent completions in the qualified sector  2

 Annual completions  2

Distribution of completions  4

Completions by type and size  4

  1. Outstanding commitments in the qualified sector  5

Commitments by type  5

Distribution of commitments  7

Commitments by type and size  9

Outstanding commitments for older persons' housing  10

  1. Completions and outstanding commitments in the  10 unqualified sector
  2. Other potential housing supply  10
  3. Comparing known housing supply with overall  11 requirements for homes in the qualified sector
  4. Key issues arising  14
  5. Unqualified sector  14

Tables

1. Housing completions in the qualified sector  3

2. Net completions of new homes in the qualified sector, by parish, 2002 – end  4 2010

3. Net completions of new homes in qualified sector, by type and size, 2010  5

4. Outstanding commitments for new homes in qualified sector, at start 2011  6

5. Housing commitments for new homes in qualified sector, by parish, @ start  7 2011

6. Outstanding commitments for new qualified sector homes, by type and size,  9

@ start 2011

7. Outstanding commitments for older persons' homes @ start 2011  10

8. Supply of homes provided for in the 2011 Island Plan, 2011-2015  11

9. Comparison between estimated requirements for new homes, 2011-2015 and  12 supply

Appendices

  1. Schedule of social rented housing completions, since 2002  15
  2. Schedule of purpose-built first-time buyer housing completions, since 2002  19
  3. Schedule of purpose-built open market lifelong homes completions, since  21 2009
  4. Schedule of social rented housing property sales on the open market, by type,  22 2004-2010
  5. Schedule of social rented housing property sales to social rent tenants (as  24 first-time buyers), by Type, 2007 - 2010
  6. Schedule of known completions due for social rented housing, by type, by end  25 2015
  7. Schedule of known completions due for first-time buyer housing, by type, by  27 end 2015
  8. Schedule of known completions due for open market lifelong homes, by type,  28 by end 2015
  9. Schedule of known completions due for social rented lifelong homes, by type,  29 by end 2015
  10. Schedule of projected sales of Housing property to first-time buyers, by type,  30 by end 2015
  11. Schedule of projected sales of Housing's social rented property on the open  30 market, by type, by end 2015
  12. Status of zoned Category A sites at 29 July 2011  31
  1. Introduction

The purpose of this report is to provide more up-to-date knowledge on housing supply, to allow comparisons with identified requirements for new homes in the Island Plan, and to assist in ensuring that an adequate supply of suitable housing will be available to meet the community's needs.

The information provided here describes the situation at the start of 2011 and effectively supplements the information included in the Department of the Environment's earlier reports entitled:

  • An Interim Review of Residential Land Availability', February 2010; and
  • Residential Land Availability Statistics @ Start 2010', June 2010.

Following the approval of the 2011 Island Plan, it is the intention to provide regular monitoring reports on housing land availability and the performance of related planning policies.

  1. Summary of findings

The evidence available on housing supply suggests that the Island is in a good position to meet overall demand for new homes during the first five years of the 2011 Island Plan. Current outstanding housing commitments and other identified sources of housing supply considerably exceed the overall requirement for 2,000 homes during the period. This is largely down to an excess in land availability for private Category B development. In contrast, the evidence suggests that the existing and potential overall supply for Category A homes at this time will only just be sufficient to meet the identified requirement for 500 homes up to the end of 2015.

Despite the findings of this review and the apparent generally favourable land availability situation at the start of 2011, there can be no room for complacency. There are some significant challenges facing the Island at this time in relation to housing provision, which require more detailed consideration. Furthermore, it is important to keep the housing situation under close scrutiny, to provide regular up-to-date information, identify any unforeseen changes in circumstances and ensure that such changes are responded to effectively and in a timely manner.

  1. Future considerations

Examples of key areas which present significant challenges and require more detailed consideration, including:

  • The provision of affordable homes' for residents and key workers;
  • The future role of social rented housing (in the light of the Whitehead Report');
  • Matching the type and size of homes supplied to identified requirements;
  • Planning to meet the future housing needs of a rapidly growing elderly population; and
  • The continuing economic downturn and the current depressed nature of the local housing market.

Housing affordability is perhaps the most important issue requiring attention at this time, given the current difficulties for people on low or modest incomes gaining access to suitable housing that they can afford. To assist the procurement of required affordable homes, the Department of Environment is currently conducting a review of the draft supplementary planning guidance for Island Plan Policy H3 (Affordable Housing), including the associated standard viability assessment model for new housing developments. It is doing so in consultation with the construction industry.

On the demand side, there is a need for more in-depth information about housing requirements to help ensure appropriate delivery of new homes across all tenures. When it is set up, the new housing gateway' will help provide better information about the numbers of affordable homes required (including social rented, shared ownership / Jersey Homebuy 2, designated first-time buyer, and self-build or other housing developed specifically at reduced costs and available through the gateway). The new Housing Needs Survey' which is scheduled to be carried out by the States Statistics Unit in 2012 will also provide valuable up-to-date and detailed information on housing requirements, including the types and sizes of homes required in each tenure group.

  1. Recent completions in the qualified sector

Annual completions

Table 1 shows the net number of completions of new homes in the qualified sector since 2002 (i.e. the adoption of the 2002 Island Plan) and allows a comparison with past trends. Despite reductions in net completions in the last three years, during the economic downturn, residential construction work since 2002 has been impressive resulting in approximately 4,700 new homes. The average building rate during the last nine years of approximately 520 new homes per year is very healthy and significantly exceeds the average rate of completions achieved in the preceding 16 years (366) during the life of the 1987 Island Plan.

The average rate for purpose-built Category A and Category B homes during the 9 years to the end of 2010 was 166 and 356 homes per year respectfully. However, the figures take no account of the proportion of the completions currently included in Category B private developments, which will have contributed to meeting identified Category A requirements.

Table 1: Housing completions in qualified sector

Completed Dwellings (net)

Year

Purpose built first- time buyer homes*5

Purpose built social rented homes*6

Purpose built open mkt l/long / retiremnt homes

Total purpose built Cat A completion s

Other demand housing (Cat B)

Total

completions

1986

107

40

 

147

232

379

1987

23

225

 

248

106

354

1988

108

136

 

244

103

347

1989

-

147

 

147

128

275

1990

17

130

 

147

289

436

1991

76

75

 

151

325

476

1992

139

130

 

269

159

428

1993

187

86

 

273

243

516

1994

81

197

 

278

175

453

1995

165

50

 

215

199

414

1996

15

70

 

85

224

309

1997

12

(137)

 

(125)

142

17

1998

-

51

 

51

186

237

1999

79

78

 

157

240

397

2000

-

60

 

60

312

372

2001

59

26

 

85

367

452

Sub-total

1068

1364

 

2432

3430

5862

Ave. annual completion 1986-2001

67

85

 

152

*3

214

*3

366

2002

*2

92

*1

290

 

382

483

865

2003

*2

161

*1

30

 

191

464

655

2004

*2

52

*1

59

 

111

349

460

2005

*2

40

*1

26

 

66

513

579

2006

*2

80

*1

207

 

287

433

720

2007

*2

184

*1

77

 

261

314

575

2008

*2

68

 *1

(-14)

 

54

171

225

2009

*2

81

*1

45

5

131

283

414

2010

*2

8

*1

2

 

10

191

201

Sub-total

766

722

5

1,493

3,201

4,694

Ave. annual completion 2002-2010

 

 

 

166

*4

356

*4

522

*1 see Appendix 1 for details; *2 see Appendix 2 for details; *3 includes lodging and staff accommodation; *4 excludes lodging and staff accommodation; *5 now includes Jersey Homebuy; *6 includes social rental lifelong homes

Distribution of completions

Most of the net increase in homes over this 9 year period (61%) was in the urban parishes of St. Helier (41%), St. Saviour (8%) and St. Clement (12%), as indicated in Table 2 below. This is very much in line with the spatial strategy' for new development set out in the 2002 Island Plan, which promoted more sustainable development concentrated in urban areas (N.B. a strategy which has been reinforced in the 2011 Island Plan).

Table 2: Net completions of new homes in the qualified sector, by parish, 2002 – end 2010

 

Parish

New Homes by Category

Total Homes Completed

%

Purpose Built Category A

*1

Category B

St. Brelade

0

269

269

5.7

St. Clement

264

278

542

11.6

Grouville

17

107

124

2.7

St. Helier

701

1244

1945

41.4

St. John

40

87

127

2.7

St. Lawrence

119

268

387

8.2

St. Martin

64

100

164

3.5

St. Mary

0

64

64

1.4

St. Ouen

42

129

171

3.6

St. Peter

82

267

349

7.4

St. Saviour

140

230

370

7.9

Trinity

24

158

182

3.9

TOTAL

1,493

3,201

4,694

100.0

*1 excluding contribution from private Category B developments.

Completions by type and size

Table 3 gives an indication of the types and sizes of the homes which were completed for Category A and Category B purposes in 2010. The majority of completions (79%) were 2- and 3-bed homes. As in 2009, the net total of 201 homes was fairly evenly spread between flat completions (42%) and house completions (58%). This is different to the preceding two years (2007 and 2008) when the great majority of completed homes were houses. Prior to 2007, the prevalent trend was for the majority of units completed being flats.

Table 3: Net completions of new homes in qualified sector, by type and size, 2010

 

Type of Home

Size of Home

Total

1-bed

2-bed

3-bed

4-bed

5-bed+

Unspecified

Category B completions

*1

Flats

20

54

17

-

-

-6

85

*2

Houses

11

10

48

34

9

-6

106

Sub-Total

31

64

65

34

9

-12

191

%

16.2

33.5

34.0

17.8

4.7

(-6.2)

100.0

Category A completions

*1

Flats

-

-

-

-

-

-

-

*2

Houses

(-19)

15

14

-

-

-

10

Sub-Total

(-19)

15

14

-

-

-

10

%

(-190)

150.0

140.0

-

-

 

100.0

TOTAL

12

79

79

34

9

-12

201

%

6.0

39.3

39.3

16.9

4.5

(-6.0)

100.0

*1 includes apartments, studios, bedsits and maisonettes; *2 includes bungalows and cottages

  1. Outstanding commitments in the qualified sector

Commitments by type

Table 4 provides details of outstanding commitments for new homes in the qualified sector' at the end of 2010. It illustrates good levels of commitments (i.e. nearly 3,000 homes), which comfortably exceed the target requirements for new homes in the first half of the 2011 Island Plan period up to the end of 2015. Of course, not all the commitments will be completed in that timeframe, but the majority should be, including:

  • the 974 Category B homes under construction at the end of 2010;
  • a proportion of both the 1500 Category B homes with existing consents, which had yet to start (supplemented by an unknown number of proposed homes which will be granted consent during the five year period 2011- 2015);
  • virtually all the 83 outstanding commitments for first time buyer homes (whether or not they were under construction at the start of 2011);
  • the commitments for Lifelong homes (approx. 350 homes) and other social rented homes under construction (approx. 100 homes).

The commitments for other social rented homes during the period show a net loss of 24 homes, which reflects the Housing Department's ongoing programme of redeveloping its outworn housing developments.

Table 4: Outstanding commitments for new homes in qualified sector, at start 2011

Outstanding Planning Permissions

Homes under

construct

ion (Net) (b)

Other commitments which may yield or involve loss of units before the end of 2015

Total

(a+b+ c)

Type of Housing

No. of New Homes (Net)

Definite, or Probable

( c )

Other possibles in the time frame

(d)

Planning in Principle Permits

Planning or Building

Permits

Total no. with consent

(a)

Purpose built convention al first time buyer  (inc. Homebuy)

-

26

26

15

42

-

83*2

Lifelong Homes

(open market)

-

40

40

3

120

-

163*3

Lifelong Homes

(soc. rented)

-

51

51

15

124

-

190*4

Other Social Rented

-

(-142)

(-142)

94

24

-

(-24)*5

Total Category A

-

(-40)

(-40)

142

310

-

412

Other demand housing

(Cat B)*6

396

1,182

*1

1,578

974

-

-

2,552

Total  (all housing)

396

1,157

1,553

1,101

310

-

2,964

*1 net of permissions which have not been advanced for 4 years or more; *2 see Appendix 7 for details ;*3 see Appendix 8 for details; *4 see Appendix 9 for details; *5 see Appendix 6 for details; *6 These figures take no account of the potential 160 or so owner occupied homes

which would be released when the owners downsize to open market Lifelong homes.

As can be seen from Appendices 6 - 9, the commitment figures for Category A homes rely to a significant degree on:

  • the remnants of development sites rezoned for the purpose under Policy H2 of the 2002 Island Plan; and
  • the fields zoned by the States in July 2008, primarily for Lifelong Homes (P.75/2008) and included in the 2011 Island Plan.

The current status of these sites is outlined in Appendix 12.

Distribution of commitments

Table 5 illustrates the availability of housing commitments by parish. As with completions over the last 9 years, most of the commitments are concentrated in the main urban parishes (76%), including St. Helier (62%) and St. Saviour (12%). The low level of net commitments in St. Clement (2%) is due, in part, to losses of homes associated with redevelopment and refurbishment of outworn housing.

Table 5: Housing commitments for net new homes in qualified sector, by parish @ start 2011

 

Parish

House Type

Outstandi ng Permissio ns

Homes under constructi on

Other Commitm ents

Total Commitments

No.

%

St. Brelade

Cat B

F-t-b

Lifelong Homes Other Social Rent

26 26 -

-

91 -

- -

- - 55 -

117 26 55 -

6.7

St. Clement

Cat B

F-t-b

Lifelong Homes Other Social Rent

50 -

42 (-147)

22 -

- 60

- -

- 24

72 -

42 (-63)

1.7

Grouville

Cat B

F-t-b

Lifelong Homes Other Social rent

66 - 20 -

23 -

- -

- - - -

89 - 20 -

3.7

St. Helier

Cat B

F-t-b

Lifelong Homes Other Social Rent

1,168 -

-

5

620 -

- 34

- - 9 -

1,788 -

9 39

61.9

St. John

Cat B

F-t-b

Lifelong Homes Other Social Rent

26 - 14 -

16 -

- -

- - - -

42 - 14 -

1.9

St. Lawrence

Cat B

F-t-b

Lifelong Homes Other Social Rent

28 -

- -

21 -

- -

- 12 -

-

49 12 -

-

2.0

St. Martin

Cat B

F-t-b

Lifelong Homes Other Social Rent

29 -

- -

16 -

- -

- - - -

45 -

- -

1.5

 

Parish

House Type

Outstandi

ng

Permissio

ns

Homes

under

constructi

on

Other

Commitm

ents

Total Commitments

No.

%

St. Mary

Cat B

F-t-b

Lifelong Homes Other Social Rent

5 - - -

6 15 18 -

- - - -

11 15 18 -

1.5

St. Ouen

Cat B

F-t-b

Lifelong Homes Other Social Rent

26 -

- -

29 -

- -

- - - -

55 -

- -

1.9

St. Peter

Cat B

F-t-b

Lifelong Homes Other Social Rent

77 - 15 -

21 -

- -

- - - -

98 - 15

-

3.8

St. Saviour

Cat B

F-t-b

Lifelong Homes Other Social Rent

71 -

- -

101 -

- -

- - 180 -

172 - 180 -

11.9

Trinity

Cat B

F-t-b

Lifelong Homes Other Social Rent

6 - - -

8 - - -

- 30 -

-

14 30 -

-

1.5

Totals

Cat B

F-t-b

Lifelong Homes Other Social Rent

GRAND TOTAL

1,578 26

91 (-142) 1,553

974 15 18 94 1,101

- 42 244 24 310

2,552 83 353 (-24) 2,964

100.0

Commitments by type and size

Table 6 gives an indication of the types and sizes of the homes to be provided from known Category A and Category B commitments at the start of 2011. The commitments cover a range of dwelling types and include nearly 2,000 flats (66%) and approximately 1,000 houses (34%). The evidence also suggests that currently in the pipeline, there are significant additional supplies of 1- and 2-bedroom accommodation (83% of which are flats) and reasonably healthy supplies of 3- and 4-bedroom family homes (80% of which are houses).

Table 6: Outstanding commitments for new qualified sector homes, by type and size, at start 2011

Type of Home

Size of Home

Total

1-bed

2-bed

3-bed

4-bed

5-bed+

Unspecified

Category B Homes with Permission and/or Under Construction

*1

Flats

728

954

194

8

-

4

1,888

*2

Houses

31

105

283

187

50

8

664

Sub-Total

759

1,059

477

195

50

12

2,552

Known Social Rented Commitments (excluding Lifelong Homes)

*1

Flats

39

(-30)

(-46)

(-4)

-

-

(-41)

*2

Houses

1

(-22)

34

3

1

-

17

Sub-total

40

(-52)

(-12)

(-1)

1

-

(-24)

Known First-time Buyer Commitments

*1

Flats

-

-

-

-

-

-

-

*2

Houses

-

-

78

5

-

-

83

Sub-total

-

-

78

5

-

-

83

Known Lifelong Homes Commitments

*1

Flats

11

100

-

-

-

-

111

*2

Houses

-

242

-

-

-

-

242

Sub-Total

11

342

-

-

-

-

353

Total

810

1,349

543

199

51

12

2,964

*1 includes apartments, studios, bedsits and maisonettes; *2 includes bungalows and cottages

Outstanding commitments for older persons' housing

At the beginning of 2011 there were outstanding commitments for approximately 350 homes aimed at the older members of the community. These might be variously described as Lifelong Homes or retirement homes and they are either for sale in the private sector or provided in the social rented sector (i.e. by Parishes, Trusts and the States). The homes in question are set out in Table 7.

Table 7: Outstanding commitments for older persons' homes @ start 2011

 

Address

Number of homes

Description

2-4, Journeaux Street, St. Helier

9

Retirement homes

Field 633, Grande Route de St Pierre, St. Peter

15

Lifelong Homes

Field 274, La Lourderie, St. Clement

42

Lifelong Homes

Fields 516, 516A, 517 and 518, St. Saviour

180

Lifelong Homes

Field 91A, Belle Vue (Lesquende), Les Quennevais, St. Brelade

55.

Lifelong Homes

Field 148, Rue des Maltieres, Grouville

20

Lifelong Homes

Fields 561 and 562, St. Mary

18

Lifelong Homes

Field 605, St. John

14.

Lifelong Homes

Total*

353

 

* This does not include redevelopments and refurbishments at existing Housing Department sites, which are producing numbers of units aimed at older, less mobile members of the community.

  1. Completions and outstanding commitments in the unqualified sector

There is currently a lack of good, comprehensive data on the supply of non- qualified accommodation (including Registered Lodging Houses, private lodgings with 5 or less lodgers and staff accommodation) and this is likely to remain the case until the new system for monitoring and regulating migration is properly up and running. Nevertheless, the situation, based on the limited information that is presently available (including the Lodging House Inspector's 2009 report) is described in An Interim Review of Residential Land Availability', Planning and Environment Department, 2010.

  1. Other potential housing supply

The 2011 Island Plan identifies a range of supply sources which can potentially generate 2,425 new homes over the first five year period 2011- 2015. These are set out in Table 8 and comprise 400 Category A and 2,025 Category B homes. It can be seen that heavy reliance is placed on the opportunities presented by the St. Helier Waterfront, town regeneration and private windfall developments located elsewhere in the built-up area.

Table 8: Supply of homes provided for in the 2011 Island Plan, 2011-2015.

 

Supply Source

Estimated Number of Units

Cat A

Cat B

Total

2002 Island Plan Category A housing sites

*1

125

-

125*1

2002 Island Plan amendment: Lifelong and first-time buyer homes

350

-

350

St. Helier Waterfront

-

600

600

Town of St. Helier regeneration

75

675

750

Windfall developments elsewhere

75

750

825

Housing in Rural Centres (IP Policy H5)

25

-

25

States Owned Land

50

-

50

*2

Less outworn sites

(-300)

-

(-300)

Total

400

2,025

2,425

*1 This is an outdated figure, in that only two sites remained to be completed at the start of 2011, with an estimated yield of 41 homes (see Appendix 12).

*2 This refers to an estimated loss of the total number of units associated with the planned re- development and upgrading of old outworn housing estates owned and managed by the States of Jersey Housing Department.

Source: States of Jersey – Island Plan, 2011

  1. Comparing known housing supply with overall requirements for homes in the qualified sector

The figures in Table 9 look to apply known and likely housing supply to estimated requirements set out in the 2011 Island Plan.

It can be seen that, in broad terms, the housing completions to-date combined with known outstanding commitments and identified supply sources more than match the identified total requirements up to the end of 2015. In fact, they greatly exceed identified total requirements by the order of 800 homes. This is largely down to an excess of land availability for private Category B development.

The Category A situation is different in that the existing and potential supply at this time just about equates to the identified requirement for 500 homes.

Table 9: Comparison between estimated requirements for new homes, 2011 – 2015 (based on 2011 Island Plan) and supply

 

 

Cat. A homes

Cat. B homes

Total homes

Identified requirements for homes 2011-2015

(based primarily on population and household modelling and an assumed net inward migration of +150 h/hs):

500

1,500

2,000

Less home completions during 2010 *1

Less Category A completions during 2010:

- Lifelong / Retirement Homes (Open Market or Social Rent)

- Other Social Rented (purpose-built)

- First-time buyer (purpose-built)

Less Cat.B completions during 2010 *2

(14) (-12) (8)

(10)

(191) (191)

(14) (-12) (8) (191) (201)

Less known outstanding Category A commitments (likely / capable of yielding before end 2015):

- Lifelong Homes (Open Market)

- Lifelong Homes (Social Rented)

- Other Social Rented (purpose built) -

First-time Buyer (purpose built) (including Homebuy)

(163) (190) (-24) (83) (412)

 

(163) (190) (-24) (83) (412)

Less Cat B commitments @ start 2011 (under construction only); *3

 

(974)

(974)

Requirements less known completions and commitments:

78

335

413

Less other supply sources identified in 2011 Island Plan and not accounted for above:

  • Town of St. Helier *4
  • Windfall Sites Elsewhere *5

Rural Centres (Policy H5 – Housing in Rural Areas)

  • St. Helier Waterfront*6
  • Surplus States Owned Sites

*9

(42)

(75) (25)

(50) (192)

(562) (396)

(216) ___ (1,174)

(604) (471) (25)

(216) (50) (1,366)

Plus remaining units to be lost through the redevelopment of outworn social rented hsg estates.*7

(-125)

 

(-125)

Projected remaining requirements to end 2015

Shortfall of approx. 11*8

Provision above target approx. 839

Provision above target approx. 828

See notes over:

Notes:

*1. These 2010 completions were not taken into account when the identified requirement

figures were rolled forward during the Island Plan Review process.

*2. This includes some Category B homes that will have contributed to meeting f-t-b needs. *3. This takes no account of:

  • Cat B consents not commenced at start 2011 but which will complete by end of 2015;
  • Cat B consents which will be granted and could complete in the period.

However, it does include some Category B homes that will contribute to meeting f-t-b needs.

*4. The 2011 Island Plan estimated a potential yield of 75 Category A homes and 675

Category B homes in the town. 146 homes are already accounted for as being under construction at Hotel Rex, Salisbury Crescent, Sunshine Hotel, Gardener & Sussex House and Sacre Coeur (33 x Cat A and 113 x Cat. B).

*5. The estimated yield is for 825 private windfall units over the 5 years between 2011 and

2015 @ a conservative 165 homes/annum. 354 units are already accounted for as being under construction outside St. Helier , thus leaving 471 units not accounted for. The Island Plan affordable housing policy will have some impact in the timeframe. It is anticipated that this will contribute the 75 affordable homes required.

*6. The 2011 Island Plan estimates a yield of 600 homes on St Helier Waterfront up to 2015.

384 homes are already accounted for as being under construction at Castle Quays, leaving 216 homes not accounted for. The balance is likely to be met from outstanding permits for Zepherus (59 homes), Esplanade Quarter (388 homes) or Caste Quays Phase II (280 homes).

*7. The 2011 Island Plan estimates a net loss of 300 social rented homes between 2011 and

2015, associated with planned redevelopment and upgrading of old outworn housing estates. The Housing Department has advised that this figure should probably be revised down to 100-150 units, given where it is currently with its refurbishment programme and taking into account recent losses and planned losses over the first 5 year period of the Island Plan.

*8. The target figure is likely to be met if one takes into account that certain planned private

Category B developments are likely to contribute directly to meeting some first-time buyer needs.

*9. Island Plan Policy H1 requires planning permissions to be secured for 150 affordable

homes on States owned land within 2 years of the Plan's adoption. It is realistic to expect that the majority of these homes will be delivered at the beginning of the second 5-year plan period.

It is important to emphasise that the conclusions reached from Tables 9 rely heavily on the following housing yield assumptions:

  • new homes will arise in good numbers from town regeneration and the St Helier Waterfront (750 homes and 600 homes respectively);
  • there will be a continuing healthy supply of private windfall developments elsewhere in the built-up area (825 homes); and
  • all the remaining sites zoned for Lifelong Homes and First-time Buyer homes in P.75/2008, will come forward for development (300 homes). The current status of these sites is given in Appendix 12.

It should also be acknowledged that the reliance placed by the States on private developers to provide need housing on zoned sites has implications for delivery times. It means that the decision about when to develop sites is a matter for the land owner and the developer and this can be affected by all manner of influences, including availability of development funding, views on the market, availability of resources to undertake development and constraints imposed by planning policies and obligation agreements. This together with the recent economic downturn has accounted for the delays experienced in advancing a number of allocated sites and approved developments.

  1. Key issues arising

Notwithstanding the relatively healthy overall land availability position, there are a number of housing issues which present challenges for the Island and require further consideration. These issues have previously been addressed in An Interim Review of Residential Land Availability', Planning Department, 2010 and include:

  • the provision of affordable homes' for residents and key workers;
  • the future role of social rented housing, in the light of the Whitehead Report';
  • the need to identify the type and size of homes required and to match these with supply; and
  • planning to meet the future housing needs of a rapidly growing elderly population.
  1. Unqualified sector

This matter is also addressed in An Interim Review of Residential Land Availability', Planning Department, 2010. Assessing the current position continues to be hampered by a lack of available data. However, from the evidence available at the time, the above report concludes that there seems no reason why the market cannot continue to be successful in meeting estimated requirements in the foreseeable future.

Appendix 1

Schedule of social rented housing completions since 2002

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

Completions 2002

16774/A/D

Florence Boot Cottages (Ph. III & IV), St. Clement

 

 

18 (- 10)

3

 

21 (-10)

19337/A PB/2001/0432

5, St. Clement 's Road, St. Helier

9

1

 

 

 

10

7215/N PB/1998/1041

Le Jardin Fleuri, (former La Motte Ford site), La Rue a Don, Grouville

 

4

12

 

 

16

424/N PB/1999/2574

Oak Tree Gardens (Elysee Estate Phase III), Trinity Hill, St. Helier

7

22

5

 

 

34

2916/P PB/2000/0892

Former Berkshire Hotel Site, 33-35, La Motte Street, St. Helier

113

 

 

 

 

113

3855/O/T PB/1998/2609

Former Postal HQ site, Mont Millais, St. Helier

4

14

27

 

 

45

6107/B B/2000/1777

Field 413 (Parish Elderly Persons), La Longue Rue, St. Martin

20

1

 

 

 

21

11550/E/1/1 PB/1998/2606

Le Geyt Flats Estate (refurb. & redevt) (Phases V & V1), St. Saviour .

 

18

12

 

 

30

7671/F/G PB/1999/1613

Field 818 (Parish Elderly Persons), Trinity

10

 

 

 

 

10

 

Sub-total (net)

163

60

64

3

 

290

Completions 2003

424 PB/2001/0477

Elysee Estate, Trinity Hill, St. Helier

 

 

 

1

 

1

2543 B/2002/0209

Parkside (former Town Park Hotel site), Pierson Road, St. Helier

1

6

8

2

2

19

2404/I B/2000/1628

Sandybrook Hospital, St. Peter

8

2

 

 

 

10

 

Sub-total (net)

9

8

8

3

2

30

Completions 2004

20067 PB/2000/1345

Victoria Place, Albert Pr, W/front (Ph. 1), St. Helier

23

51

4

 

1

79

NONE P/2003/0627

Le Squez Estate (Phase 1A), St. Clement

 

(8)

(12)

 

 

(20)

 

Sub-total (net)

23

43

(8)

 

1

59

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

Completions 2005

11150/E PB/1999/0188

John Wesley Apartments (11,13 & 13A, Lempriere Street and 1-3, Canon Street), St. Helier

17

23

1

 

 

41

3764/Y PB/2000/2134

Clement Court, Ann Street, (former Cleveland Garage / St. Helier Garages ), (Phase 1), St. Helier Jersey Homes Trust

21

 

5

 

 

26

4628 B/2004/0302

Le Marais, Low Rise (Phase 1), St. Clement

(-21)

(-15)

 

 

 

(-36)

2884 B/2003/2646

Le Squez Estate (Phase 1A), St. Clement

 

1

 

 

 

1

4374 B/2003/1156

Victoria Cottage Homes (K Block), St. Saviour 's Hill, St. Saviour

3 (6)

 

 

 

 

3 (6)

4374 B/2004/1257

61 and 62, Victoria Cottage Homes, St. Saviour 's Hill, St. Saviour

1 (-2)

 

 

 

 

1 (-2)

4374 B/2004/1256

48 and 49, Victoria Cottage Homes, St. Saviour 's Hill, St. Saviour

1 (-2)

 

 

 

 

1 (-2)

4374 B/2005/0541

33, Victoria Cottage Homes, St. Saviour 's Hill, St. Saviour

1 (-2)

 

 

 

 

1 (-2)

 

Sub-total (net)

11

9

6

 

 

26

Completions 2006

1537 B/2003/0228

Phillips House, Victoria Street,, St. Helier , Les Vaux Housing Trust

15

3

 

 

 

18

179/G B/2002/1833

La Folie Estate, Parkinson Drive, St. Lawrence

3

14

 

 

 

17

4628 B/2004/0302

Le Marais Low Rise (Phase 1), St. Clement

14

 

 

 

 

14

8871 B/2004/0259

Fields 786 and 787 (Westview Farm), La Rue des Cosnets, St. Ouen (H2 site) community homes

6

 

 

 

 

6

11097 P/2006/2648

Le Coin, Ann Street / Charles Street, St. Helier Unoccupied since 2006 – approved temp. car park

 

(16)

 

 

 

(16)

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

15836 B/2004/0090

Le Benefice, (extension to former Hodge Nurseries), Fields 89, 89A, 90, 92A & 93, St. Clement (H2 site) CTJ Housing Trust

 

 

64

9

 

73

100/JA B/2002/1292

Le Coie Hotel Site, Janvrin Road, St. Helier , Jersey Homes Trust

44

51

 

 

1

96

1380 B/2006/0605

33-34, Grassett Park, St. Saviour

 

 

(2)

 

1

1 (2)

 

Sub-total (net)

82

52

62

9

2

207

Completions 2007

1365 B/2003/0288 B/2004/0655

Le Grand Clos

Field 1218, Mont a l'Abbe, St. Helier (H2 site) Jersey Homes Trust

14 (ret)

6

28

6

 

14 flats 40 houses

2884 P/2003/2646

Le Squez Estate (Phase 1B), Les Cloches,

St. Clement

15

3

5

2

 

18 flats 7 houses

2884 B/2005/0346

Le Squez Estate (day centre and flats),

St. Clement

2

 

 

 

 

2 flats

4628 P/2006/0718

Le Marais Estate Low Rise (Phase 2),

St. Clement

(-28)

(-20)

 

 

 

(-48) flats

P/2005/1998 tenure swap with Bagot Manor site

Clos Le Gallais, Field 1370, La Rue de Mont Sejour, St. Helier (H2 site)

Jersey Homes Trust

 

2

11

 

 

13 houses

16320 B/2004/1283 U/C

Clos Des Charmes, Fields 181, 182 & 183, La Route de la Pointe,

St. Peter (H2 site)

CTJ Housing Trust

12

3

16

 

 

12 flats 19 houses

 

Sub total (net)

15

(-6)

60

8

 

77

Completions 2008

3289/7514

Field 40, La Rue du Maupertuis, St. Clement (H2 site)

Les Vaux Housing Trust

 

 

10

 

 

10 houses

1380 B/2008/0839

33-34, Grasett Park, St. Saviour

 

 

2

 

(-1)

2

(-1) houses

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

P/2006/0048

Field 690A, Maufant, St. Martin (H2 site) Jersey Homes Trust

 

 

19

 

 

19 houses

3764/Y PB/2000/2134

Clement Court, Ann Street (former Cleveland / St. Helier Garages), (Ph 2), St. Helier .

6

 

 

 

 

6 flats

3636 P/2005/1424 B/2006/0152

Aquila Youth Centre, Great Union Road,

St. Helier (over 65's) Les Vaux Housing Trust

26 ret

 

 

 

 

26 ret flats

3511 P/2008/2409

Ann Court, Ann Place, St. Helier (empty: late 2008)

(-33)

(-34)

(-3)

 

 

(-70) flats

 

33, 35, 37 & 39, Ann St. and 1 & 2, Clifton Pl., St. Helier (empty: late 2008)

 

(-4) (-2)

 

 

 

(-4) flats (-2) houses

 

Sub total (net)

(-1)

(-40)

28

 

(-1)

(-14)

Completions 2009

4628 B/2006/1011

Le Marais Estate (low rise) (Ph 2), St. Clement

18

1

24

4

 

47

4374 B/2009/0623

1, Victoria Cottage Homes, St. Saviour

(-2)

 

 

 

 

(-2)

 

Sub-total (net)

16

1

24

4

 

45

Completions 2010

2884 P/2007/2849

Le Squez Estate (bungalows), Le Squez, St. Clement

(-19)

 

 

 

 

(-19) bungalows

4374 P/2006/0623

Victoria Cottage Homes, St. Saviour 's Hill,

St. Saviour

 

1

 

 

 

1 house

P.75/2008 7671 P/2008/2471 B/2009/0304 B/2009/0331 B/2009/0337

Field 818 and part Field 873, Trinity

(LIFELONG HOMES)

 

14

 

 

 

14 bungalows

2206/1365 B/2009/0038

Uplands Hotel – Phase 1, Field 1218, Mont-a- l'Abbe, St. Helier *1

 

 

6

 

 

6 houses

 

Sub-total (net)

(-19)

15

6

 

 

2

Total completions

299

142

250

27

4

722

*1 The 6 homes completed in 2010 at Uplands (Field 1218), Mont-a-l'Abbe for Homebuy are likely to become social rented, if they cannot be sold for Homebuy, under the terms of the associated POA. The revised Homebuy mechanism has yet to be brought back to the States of Jersey for approval.

Appendix 2

Schedule of purpose built first time buyer housing completions since 2002

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

Completions 2002

6262/S B/2000/!907

L'Abri, (Former Hodge Nurseries), La Grande Route de la Cote,

St. Clement

 

 

34

 

 

34 houses

7215

Le Jardin Fleuri, (former La Motte Ford site), La Rue a Don, Grouville

 

 

1

 

 

1 house

4169/K B/2000/5010

Field 1078, Sion, La Rue des Houguettes, St. John

 

1

39

 

 

40 houses

16840/C PB/2000/1974

Field 615, La Rue de Patier, St. Saviour

 

 

17

 

 

17 houses

 

Sub-total

 

1

91

 

 

92

Completions 2003

1377/X P/1998/2042

Woodville Hotel, St. Saviour 's Road, St. Helier

4

55

 

 

 

59 flats

20067 PB/2000/1345

Albert Place, Albert Pier, The Waterfront (Phase 1), St. Helier

29

37

4

 

 

70 flats

18961 PB/2002/0338

Fields 378 & 379 & Field Cottage, La Rue a la Dame, Five Oaks, St. Saviour

 

 

22

10

 

32 houses

 

Sub-total (net)

33

92

26

10

 

161

Completions 2004

14060 PB/2002/0709

Bagot Manor Farm, Bagot Manor Road, St. Saviour

 

 

21

 

 

21 houses

18961 PB/2002/1321

Fields 378 and 379 and Field Cottage, La Rue a la Dame, St. Saviour

 

 

20

11

 

31 houses

 

Sub-total (net)

-

-

41

11

 

52

Completions 2005

NONE B/2003/1384

Le Squez (Phase 1A), La Gambrette', St. Clement

 

 

14

4

 

18 houses sold 2007

8871 B/2004/0259

Fields 786 and 787 (Westview Farm), La Rue des Cosnets,

St. Ouen (H2 site)

 

 

22

 

 

22 houses

 

Sub-total (net)

 

 

36

4

 

40

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

Completions 2006

4628 B/2004/0302

Le Marais Low Rise (ph 1), La Selliere', St. Clement

 

 

23

 

 

23 houses sold 2007

8871 B/2004/0259

Fields 786 and 787 (Westview Farm), La Rue des Cosnets,

St. Ouen (H2 site)

 

 

14

 

 

14 house

5025 B/2004/0615

Field 203 (Le Clos Corvez), part 204 & 252, Jambart Lane, St. Clement (H2 site)

 

 

30

13

 

43 houses

 

Sub-total (net)

 

 

67

13

 

80

Completions 2007

1365 B/2003/0228 U/C

Le Clos Vaze, Field 1218, Mont a l'Abbe, St. Helier (H2 site)

 

26

43

 

 

69 houses

2884 P/2003/2646

Les Cloches, Le Squez (Phase 1B), St. Clement

 

5

31

4

 

40 houses sold 2007

4677

5025 B/2004/0615

Le Clos Corvez, Field 203, part 204 & 252, Jambart Lane, St. Clement (H2 site)

 

 

33

 

 

33 houses

16320 B/2004/1283

Clos Des Charmes, Fields 181, 182 & 183, La Route de la Pointe,

St. Peter (H2 site)

9

2

30

 

 

30 houses 11 flats

14060 PB/2002/0709

Field 812A, Bagot Manor Farm, St. Saviour

 

 

1

 

 

1 house

 

Sub-total (net)

9

33

138

4

 

184

Completions 2008

14060 B/2005/0506 Tenure swap F.1370, St. Helier

Field 812A, Bagot Manor Farm, St. Saviour

 

 

15

 

 

15 houses

3289 B/2006/1217

Field 40, La Rue de Maupertuis, St. Clement (H2 site)

 

 

13

 

 

13 houses

None P/2006/2489

La Providence, Fields 848, 851, 853 & 854, Bel Royal, St. Lawrence (H2 site)

 

 

11

5

 

16houses

None P/2006/0048

Field 690A, Maufant, St. Martin (H2 site)

 

 

24

 

 

24 houses

 

Sub-total

 

 

63

5

 

68

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

Completions 2009

NONE B/2007/0424

La Providence, Bel Royal, St. Lawrence (H2 site)

 

 

17

18

 

35 houses

NONE B/2007/0424

La Providence, Bel Royal, St. Lawrence

(H2 site – HOMEBUY)

 

 

46

 

 

46 houses

 

Sub-total (net)

 

 

63

18

 

81

Completions 2010

2206/1365 B/2009/0038

Uplands – Phase 1, Field 1218, Mont-a-l'Abbe,

St. Helier

Approval was also for 6 HOMEBUY units, but these are now likely to become

Social Rented *1

 

 

8

 

 

8 houses

 

Sub-total (net)

-

-

8

-

-

8

Total completions

42

126

533

65

-

766

*1 At the start of September 2011, the 6 completed Homebuy units remained unoccupied. Due to the terms of the POA, these units are likely to become social rented, if they cannot be sold for Homebuy. Homebuy cannot be currently met, because the revised Homebuy mechanism has yet to be brought back to the States of Jersey for approval. In the interim, for the purposes of this report, the 6 homes in question will be classed as Social Rented homes.

Appendix 3

Schedule of purpose built open market lifelong homes completions since 2009

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

Completions 2009

None B/2007/0424

La Providence, Bel Royal, St Lawrence

 

5

 

 

 

5 houses

 

Sub-total (net)

 

5

 

 

 

5

Total completions

 

5

 

 

 

5

Schedule of social rented housing property sales on the open market, by type, 2004- 2010

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

2004

 

101, Don Road, St. Helier

 

 

1

1

 

2 flats

 

Sub-total (net)

-

-

1

1

 

2

2005

 

Amy's House, La Route de St. Catherine Fief de la Reine, St. Martin

 

1

 

 

 

1 house

 

Winchester House, Winchester Street, St. Helier

3

 

 

 

 

3 flats

 

Old Eastern Telephone Exchange & Cottage, La Rue de la Hambie Sous La Hougue, St. Saviour

 

 

1

 

 

1 house

 

Old Station House, Corbiere, St. Brelade

 

 

 

1

 

1 house

 

Caledonia Close, St. Helier

8

 

 

 

 

8 flats

 

L'Hopital, La Route de St. Catherine De Rozel, St. Martin

 

1

 

 

 

1 house

 

Sub-total (net)

11

2

1

1

 

15

2006

 

La  Falaise,  La  Rue  du Flicquet, St. Martin

 

1

 

 

 

1 house

 

Sub-total (net)

 

1

 

 

 

1

2007

 

17, Devonshire Place, St. Helier

 

 

1

 

 

1 house

 

19, Devonshire Place, St. Helier

 

1

 

 

 

1 house

 

4, Boulevard Avenue, St. Helier

 

 

 

 

1

1 house

 

39, Midvale Road, St. Helier

 

 

 

 

1

1 house

 

Sub-total (net)

 

1

1

 

2

4

2008

 

Medina, Seale Street, St. Helier

3

 

 

 

 

3 flats

 

Sub-total

3

 

 

 

 

3

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

2009

 

10, Duhamel Place, St. Helier

2

 

1

 

 

3 flats

 

12, Duhamel Place, St. Helier

2

 

1

 

 

3 flats

 

6, Pomona Road, St. Helier

 

 

1

 

 

1 house

 

17, Charles Street, St. Helier

 

 

 

1

 

1 house

 

Sub-total

4

 

3

1

 

8

2010

 

30, Clos des Sables, St. Brelade

 

 

1

 

 

1 house

 

Archirondel Cottage, Route de la Cote, St. Martin .

 

1

 

 

 

1 house

 

Belleville, Rue du Crocquet,, St. Brelade

 

 

 

 

1

1 house

 

97, Don Road, St. Helier

 

 

 

1

 

1 house

 

Modena, Clarence Road, St. Helier

 

1

 

 

 

1 house

 

8, Belmont Road, St. Helier .

 

 

 

 

1

1 house

 

Sub-total

 

2

1

1

2

6

Total sales

18

6

7

4

4

39

Note: The States Social Housing Property Plan, 2007-2016' provides for the sale of 27 houses on the open market.

Schedule of social rented housing property sales to social rent tenants (as first-time buyers), by type, 2007-2010

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

2007

 

La Cambrette, (Le Squez Phase 1A), St. Clement

 

 

14

4

 

18 houses

 

Le Selliere, (Le Marais Low Rise Phase 1), St. Clement

 

23

 

 

 

23 houses

 

Les Cloches, (Le Squez Phase 1B), St. Clement

 

5

12

4

 

21 houses

 

Sub-total

 

28

26

8

 

62

2008

 

Les Cloches, (Le Squez Phase 1B), St. Clement

 

 

19

 

 

19 houses

 

Clos Des Sables, St. Brelade

 

 

2

 

 

2 houses

 

Grasett Park, St. Saviour

 

 

4

1

 

5 houses

 

Les Houmets, Grouville

 

 

1

 

 

1 house

 

Le Bel Collas, Gorey Village, Grouville

 

 

1

 

 

1 house

 

Sub-total

 

 

27

1

 

28

2009

 

Oak Tree Gardens, St. Helier

 

 

8

 

 

8

 

Grasett Park, St. Saviour

 

 

6

 

 

6

 

26, La Rue De Carteret , St. Saviour

 

 

1

 

 

1

 

Sub-total

 

 

15

 

 

15

2010

 

Various

 

2 1

4

 

 

2 flats 5houses

 

Sub-total

 

3

4

 

 

7

Total sales

 

31

72

9

 

112

Note: The States Social Housing Property Plan, 2007-2016' provides for the sale of some 773 houses and flats on a shared equity basis.

Schedule of known completions due for social rented housing, by type, by end 2015

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

Completions due 2011

1365 P/2007/1213 Permit

Units 17 & 18, Le Grand Clos, St. Helier (Jersey Homes Trust – covert to 6-bed home)

 

 

(-2)

 

1

(-2)

1 house

4867 P/2008/1677 B/2009/0930 Permit

Clos du Paradis, La Pouquelaye, St. Helier

 

 

(-24)

 

 

(-24) houses

13439 P/2001/2087 B/2003/0592 B/2007/1265 U/C (complete June 2011)

Salisbury Crescent, La Rue Le Masurier,

St. Helier

24 1

 

7

2

 

24 flats 10 houses

P/2009/2082 B/2010/0602 U/C

Field 633, La Grand Route de St Pierre, St. Peter (LIFELONG HOMES)

 

15

 

 

 

15 bungalows

 

Sub-total (net)

25

15

(-19)

2

1

24

Completions due 2012

4867 P/2008/1677 B/2009/0930 Permit

Clos du Paradis, La Pouquelaye, St. Helier

 

 

29

1

 

30 houses

2884 P/2009/0780 B/2009/0876 U/C

Le Squez Estate (Phase 2a & 2b), Le Squez,

St. Clement

21

3 15

21

 

 

24 houses 36 flats

P.75/2008 8053 P/2009/1600 B/2010/0234 U/C

Fields 561 and 562, St. Mary

(LIFELONG HOMES)

 

15

 

 

 

15 bungalows

 

Sub-total (Net)

21

33

50

1

 

105

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

Completions due 2013

20609/13426 P/2010/0791 Decision pending Definite

2-4, Journeaux Street, St. Helier

(LIFELONG HOMES)

9

 

 

 

 

9 flats

P.75/2008 7172 P/2009/2388 Permit

No Building Application

Field 274, La Lourderie, St. Clement (LIFELONG HOMES)

 

3 13

 

 

 

3 bungalows 13 flats

P.75/2008 P/2010/0126 B/2011/0280 Decision pending

Field 148, Rue des Maltieres, Grouville (LIFELONG HOMES)

 

20

 

 

 

20 bungalows

New application to be submitted

Le Squez Estate (Phase 2c) Le Squez,

St. Clement

10

9

2 3

 

 

21 flats 3 houses

 

Sub-total (Net)

19

45

5

 

 

69

Completions due 2014 and 2015

2884 P/2007/2849 Permit

Le  Squez  (flats),  Le Squez, St. Clement

(-16)

(-54)

(-30)

 

 

(-100) flats

2884 P/2007/2849 Permit

Le  Squez  Estate (houses),  Le  Squez, St. Clement

 

(-25)

(-18)

(-4)

 

(-47) houses

1270 P/2009/2419 Planning App. decision still pending

Field  91A,  Belle  Vue (Lesquende),  Les Quennevais,  St.  Brelade (LIFELONG HOMES)

 

35

 

 

 

35 flats

P.75/2008 16840 P/2010/1901 Decision pending

Fields  516,  516A,  517 and 518, St. Saviour

(LIFELONG HOMES)

 

48 32

 

 

 

48 flats 32 bungalows

 

Sub-total (Net)

(-16)

36

(-48)

(-4)

 

(-32)

Total  completions  due  (net)  2011  to end 2015

49

129

(-12)

(-1)

1

166

Note: Plans to convert 39 bedsits to 22no. 1-bed flats at Hampshire Gardens, Aquila Road, St. Helier have been the subject of preliminary advice, but will not be implemented in the above timeframe.

Schedule of known completions due for first-time buyer housing, by type, by end 2015

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

Completions due by end 2015

P/2007/0223 B/2007/0654 B/2009/0397 Started & stopped

Fields 190, 191 & 192, La Rue de la Sergente,

St. Brelade

(H2 site)

 

 

14

 

 

14 houses

P/2007/0223 B/2007/0654 B/2009/0397 Started & stopped

Fields 190, 191 & 192, La Rue de la Sergente,

St. Brelade

(H2 site)

HOMEBUY

 

 

12

 

 

12 houses

19304

Prelim. Advice PA/2009/2243 Still no app.

Field 873, Bel Royal, St. Lawrence (H2 site)

 

 

7

 

 

7 houses

19304

Prelim. Advice PA/2009/2243 Still no App.

Field 873, Bel Royal, St. Lawrence (H2 site) HOMEBUY

 

 

5

 

 

5 houses

(P.75/2008) 8053 P/2009/1600 B/2010/0234 U/C

Fields 561 and 562, St Mary

 

 

10

5

 

15 houses

(P.75/2008) P/2011/0618 Decision pending

Field 578, Trinity

NB – App for 43 FTB, but ignores required tenure split

 

 

30

 

 

30 houses

Total completions due

 

 

78

5

 

83

Schedule of known completions due for open market lifelong homes, by type, by end 2015

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

Completions due by end 2015

8053 P/2009/1600 B/2010/0234 U/C

Fields 561 and 562, St. Mary (P.75/2008)

 

3

 

 

 

3 bungalows

P/2010/0112 Permit

Later building app B/2011/0060

Field 605, Route du Nord, St. John (P.75/2008)

(scheme U/C May 2011)

 

14

 

 

 

14 bungalows

7172 P/2009/2388 Permit

No building app.

Field 274, La Lourderie, St. Clement (P.75/2008)

2

20 4

 

 

 

20 cottages 6 flats

16840

Prelim. Advice

Fields 516, 516A, 517 and 518, St. Saviour (P.75/2008) *

 

100

 

 

 

100 cottages

1270 P/2009/2419 Decision still pending

Field 91A, Belle Vue, (Lesquende), Les Quennevais, St. Brelade

 

20

 

 

 

20 houses

Total completions due

2

161

 

 

 

163

* Plus 42-bed residential care home

Schedule of known completions due for social rented lifelong homes, by type, by end 2015

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

Completions due by end 2015

4305 P/2010/0126 Permit

Later building app. B/2011/0280

Field 148, Rue des Maltières, Grouville (P.75/2008)

 

20

 

 

 

20 bungalows

8053 P/2009/1600 B/2010/0234 U/C

Fields 561 and 562, St. Mary (P.75/2008)

 

15

 

 

 

15 bungalows

7172 P/2009/2388 Permit

Field 274, La Lourderie, St. Clement (P.75/2008)

 

3 13

 

 

 

3 bungalows 13 flats

16840

Prelim. Advice

Fields 516, 516A, 517 and 518, St. Saviour (P.75/2008)

 

48 32

 

 

 

48 flats 32 bungalows

1270 P/2009/2419 Planning App. pending

Field 91A, Belle Vue, (Lesquende), Les Quennevais, St. Brelade

 

35

 

 

 

35 flats

P/2009/2082 B/2010/0602 Permit

Field 633, La Grand Route de St Pierre, St. Peter

 

15

 

 

 

15 bungalows

20609/13426 P/2010/0791 Definite

2-4, Journeaux Street, St. Helier

9

 

 

 

 

9 flats

Total completions due

9

181

 

 

 

190

N.B. Land northeast of Maison St. Brelade zoned in (P.75/2008) for extension to nursing home (22 single bed units)

Schedule of projected sales of housing property to social rented tenants (first-time buyers), by type, by end 2015

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

2011

 

Up to 10 sales

1

 

6

1

 

8

2012

 

Up to 10 sales

 

 

 

 

 

10

2013

 

Up to 10 sales

 

 

 

 

 

10

2014

 

Up to 8 sales

 

 

 

 

 

8

2015

 

Up to 8 sales

 

 

 

 

 

8

Total sales due

 

 

 

 

 

44

Appendix 11

Schedule of projected sales of housing social rented property on the open market, by type, by end 2015

 

Ref.

Site

Units by Type

1 bed

2 bed

3 bed

4 bed

5 bed

Total

2011

 

La Grande Maison 2 & 3, Le Grand Cotil, St. Martin

 

1

1

 

 

2

 

Britannia House, La Rue de la Mare des Pres, St. John

 

2

2

1

 

5

 

2, Hungerford Villas, Vauxhall Street, St. Helier

 

 

 

 

1

1

 

La Grande Maison Cottages 1&2, Le Grand Cotil,

St. Martin

 

2

 

 

 

2

 

Sub-total

 

5

3

1

1

10

2012-2015

 

None yet confirmed

 

 

 

 

 

 

Total sales due

 

5

3

1

1

10

Note: The States Social Housing Property Plan, 2007-2016' provides for the sale of 27 houses on the open market.

Status of Zoned Category A sites (at 29 July 2011

Remaining sites (H2) from 2002 Island Plan

Of the 11 sites originally zoned for Category A housing in the 2002 Island Plan, two remain to be developed and these remained zoned under Policy H2 of the 2011 Island Plan.

  • H2 (8) Field 190 – 192, La Rue Sergente, St Brelade (indicative yield: 27 homes) Planning permission for 26 homes (P/2007/0223) was granted in February 2008 and was followed by Building Permission (B/2007/0654) in December 2008. A revised building application (B/2009/0397) for 26 homes was approved in December 2009. Work started on some preliminary site works in July 2009, but was halted soon afterwards.

At the time, the developer put the delays down to the impact of the credit crunch, including increased difficulties in obtaining development finance and the lack of available / affordable mortgage finance for prospective purchasers. However, work started again in August / September 2011 and the project is scheduled to be completed in Autumn 2012.

  • H2 (10) Field 873, St Lawrence (indicative yield: 14 homes)

More recently, because of the topography and the restricted nature of the site, the Department took the view that this site can only accommodate a Category A housing development for 10 dwellings, providing 5 first time buyer and 5 Jersey Homebuy dwellings.

Preliminary advice for an initial scheme of 12 dwellings (PA/2009/2243) was given in March 2010, but despite the development of several sketch schemes, a planning application has yet to be submitted.

Due to uncertainties about development finance, including the likely amount of subsidies required to achieve Homebuy dwellings, it is possible that the site will now be sold on.

Sites approved by the States of Jersey in 2008 (P.75/2008)

In July 2008, the States of Jersey approved Projet 75/2008, which rezoned 8 sites throughout the Island for Category A housing and primarily for Lifelong Homes. These sites remain zoned under Policy H2 of the 2011 Island Plan. Their current status is as follows:  

  • Fields 818 and part of Field 873, Trinity (indicative yield: 12 x Social Rented Lifelong Homes)

Planning permission (P/2008/2471) granted for 14 lifelong dwellings in February 2009. Building permission followed (B/2009/0304, B/2009/0331 and B/2009/0337) in July 2009. Work started in October 2009 and was completed in August/September 2010.

  • Land north east of Maison St. Brelade (indicative yield: extension to form 8 units of accommodation)

Planning permission (P/2008/2065) granted for a 21 bedroom extension to Maison St Brelade in February 2009. Building consent (B/2009/1208) followed in February 2010. Work started in January 2011.

  • Fields 561 and 562, St. Mary (stipulated yield: 33 homes – a mix of f-t-b and both social rented and open market Lifelong homes)

Planning permission (P/2009/1600) granted for 33 dwellings in November 2009, providing a mix of first-time buyer, open market lifelong dwellings for the over-55s and lifelong dwellings for social rent. The approval was subject to a planning obligation being entered into. Building consent (B/2010/0234) followed in June 2010. Work started in June 2010.

  • Field 274, La Lourderie, St. Clement (indicative yield: 34 Lifelong homes) Preliminary planning advice was given in October 2009. Planning permission (P/2009/2388) granted in June 2010 for 42 lifelong dwellings for older people

(over 55). A Building Application has yet to be submitted.

  • Field 605, St. John (indicative yield: 16 Lifelong homes)

Planning permission (P/2010/0112) granted in December 2010 for 17 open market lifelong dwellings for older people (over 55). Building consent (B/2011/0060) for 14 open market lifelong homes followed in April 2011. Work started in May 2011.

The development of this site is linked with the development of Field 148 Grouville (see comments for next site) and it has been necessary for the developer to obtain agreements with the Parish Constables in question and negotiate necessary land swaps.

  • Field 148, Rue des Maltières, Grouville (indicative yield: 20 Lifelong homes) Planning permission (P/2010/0126) granted in December 2010 for 20 social rent lifelong dwellings for the Parish of Grouville . Building consent (B/2011/0280) followed in July 2011.

Field 605, St. John and Field 148, Grouville will be tied together with a planning obligation agreement which will deliver a 45% open market life-long homes on Field 605 and 55% social rent homes on Field 148 (reflecting the wish of the owner to offer all the homes built on Field 148 to the Parish).

  • Fields 516, 516A, 517 and 518, St. Saviour (indicative yield: 98 open market Lifelong homes and 80 social rented Lifelong homes)

There were prolonged discussions with the former owner / developer which centred around the development of a mixed tenure retirement village, initially consisting of approximately 98 no. open market and 80 no. social rent lifelong dwellings (for people over 55). The initial proposals also included a residential care and dementia home, guardian accommodation, indoor and outdoor recreational facilities, shop, surgery, car parking and amenity space, and a public car park to relieve potential on-street parking in Chasse Brunet. The former owner/developer also reached an agreement with the Parish of St Saviour to provide them with thirty social rent lifelong dwellings free of charge.

In July 2009, the Minister for Planning and Environment introduced a requirement for Environmental Impact Assessments (EIAs) to be carried out on large residential schemes and because of the size of this development an EIA was been requested.

The current developer (Dandara) obtained EIA advice on a scheme for 111 dwellings and 110 apartments in October 2010. An amended planning application (P/2010/1901) was submitted in December 2010, to construct a retirement village comprising 48 social rented apartments, 32 social rented bungalows, 100 private cottages, a care home and a community centre. The decision is still pending.

  • Field 578, Trinity (indicative yield: 36 homes - a mix of f-t-b and social rented Lifelong homes)

A planning application (P/2011/0618) was submitted in June 2011 for 43 first-time buyer homes. This follows a review of the housing mix for the site by the Constable and is at odds with what the States originally zoned the land for. A decision is still pending.

Other recent Category A proposals

  • Le Squez Estate Redevelopment (Phase 2), St Clement

Planning permission (P/2009/0780) in July 2009 for redevelopment to provide 76 Category A dwellings (42 flats and 32 houses). Building consent (B/2009/0876) followed in February 2010. Work started in July 2010.

  • Uplands Hotel (Field 1218), St. Helier

An additional planning permission (P/2009/1092) was granted in January 2011 for the northern part of the Field 1218 at Uplands Hotel (Phase 2). The proposals are for 10

Category A dwellings (5 first time buyer and 5 Jersey Homebuy). Building consent (B/2010/0659) followed in August 2010. Work started on site in February 2011.

  • Field 91A (Lesquende), Belle Vue, St. Brelade

A planning application was received from Jersey Property Holdings (P/2009/2419) in December 2009 for a mix of approximately 36 apartments and 24 dwellings for older people (over 55) and is currently pending.

  • H3 (12) Field 633, La Verte Rue, St Peter

Planning permission (P/2009/2082) was granted in June 2010 to the Parish of St. Peter for 14 social rented lifelong retirement homes and 1 warden's unit. Building Consent (B/2010/0602) followed in July 2010. Work started in March 2011.