Skip to main content

Land Transactions under Standing Order 168(3) – Office accommodation project – Exchanges of land for electricity substations

This content has been automatically generated from the original PDF and some formatting may have been lost. Let us know if you find any major problems.

Text in this format is not official and should not be relied upon to extract citations or propose amendments. Please see the PDF for the official version of the document.

STATES OF JERSEY

LAND TRANSACTIONS UNDER STANDING ORDER 168(3) – OFFICE ACCOMMODATION PROJECT – EXCHANGES OF LAND FOR ELECTRICITY SUBSTATIONS

Presented to the States on 22nd September 2022 by the Minister for Infrastructure

STATES GREFFE

2022  R.128

2

REPORT

Decision(s):  Under  Standing  Order  168(3),  the  Minister  for  Infrastructure  hereby notifies the States that he has accepted the recommendation of Jersey Property Holdings to agree to the following –

Land transaction –

To  authorise  the  Public  to  enter  into  two  separate  contracts  with  Jersey Electricity PLC (JE), to enable the construction of a new secondary electricity substation on the site of the government's new office accommodation project on public land on the site of the former Cyril Le Marquand House, St Helier.

The Minister hereby authorises, as applicable, the Attorney General and the Greffier of the States to pass any contract which is required to be passed on behalf of the Public; and the Director of Property Holdings to conclude any contract which is required to be concluded on behalf of the Public.

After the expiry of 15 days following presentation to the States the transactions may be concluded.