Skip to main content

Integrated Technology Solution - Follow up

The official version of this document can be found via the PDF button.

The below content has been automatically generated from the original PDF and some formatting may have been lost, therefore it should not be relied upon to extract citations or propose amendments.

28 April 2023

jerseyauditoffice.je  

R.67/2023

Contents

Summary  3

Introduction  3

Key findings  3

Conclusions  5 Objectives and scope of the review 6 Detailed findings  7

Framework for review  7

Purpose  8 Value  11

Programme set up 15

Delivery variation and management 19 Appendix One – Audit Approach  23 Appendix Two – Summary of Recommendations and Area for Consideration  25

Summary

Introduction

  1. The Integrated Technology Solution (ITS) programme was launched in early 2020 and is intended to enable the Government to use modern, cloud-based systems for finance, human resources (HR), procurement and asset management. Release One of the ITS programme went live on 1 January 2023, followed shortly afterwards by two modules of Release Two (Performance Management and Learning and Development).
  2. In October 2021, the Comptroller and Auditor General (C&AG) issued a report ICT Cloud Implementation – Integrated Technology Solution that evaluated:

the first phase of implementation of the new taxation revenue management system and considered the lessons that can be learned for future projects; and

the design and delivery of the ITS programme up to the end of August 2021.

  1. The C&AG made 16 recommendations for the Government of Jersey to implement as the ITS programme progressed. All of the recommendations were accepted for implementation.
  2. This follow up review has considered whether the previous recommendations have been implemented and whether the ITS programme has followed best practice in the lead up to the go live' date for releases one and two.
  3. The review has considered the operation of the ITS programme to the end of November 2022 as well as the go live' decision at the end of December 2022. I have not reviewed the detailed functionality and operation of the ITS programme since releases one and two went live in January 2023. I have therefore not considered the operational problems that have been experienced in the live systems.

Key findings

  1. The key findings from my review are as follows:

the ITS programme remains an essential element to the future stability of the business operations of the States of Jersey. The previous applications used for finance were out of date and therefore unsupported and represented a strategic risk in relation to adopting modern business processes and reducing cyber security risks

an area of particular strength in the operation of the ITS programme relates to delivery and variation management, specifically the monthly reporting to the programme's Strategic Oversight Board (SOB). The reporting model adopted for the SOB and the strong financial management and governance which it demonstrates are areas of strength in the programme and should be considered for future programmes

the Government has de-coupled longer-term benefits realisation from the ITS programme, with the programme closing at the end of 2023. The result is that programme-level responsibility and monitoring for any benefits realisation beyond 2023 will cease. The formal arrangement for the oversight and governance of the realisation of benefits beyond 2023 is unclear. In addition, ITS-related benefits are not planned to be tracked beyond the end of 2026. Given the long-term investment in the new applications and the slower realisation of benefits than originally expected, I would expect the formal monitoring and reporting of benefits to be extended to 2030 if best practice is to be demonstrated

project level risk management was working effectively at a detailed level at the time of my fieldwork. There was clear evidence of detailed project risks being recorded, escalated and mitigated. However the key strategic risks in relation to the programme were not evident in the documentation provided. The strategic risks of the programme that I would have expected to have been documented as the programme progressed include:

  • the risks associated with the continued adoption of a big bang' approach to implementation for the whole of the States of Jersey rather than adopting a phased implementation by functional area or department. While a big bang' approach simplifies data migration to the new systems, a phased implementation would have allowed teething problems' to be identified and resolved without affecting the whole of the States of Jersey
  • the risk of the lack of formal, tested, contingency plans should it be necessary to revert to previous systems; and
  • the risks that were evident in the progress of the transition of the existing Supply Jersey users to the new SAP Ariba procurement system

the full implications of releasing major functionality, in particular in relation to the impact on the end user community, should be more fully assessed. The risks and benefits of releasing major functionality should be set out to inform decision making. In practice, several problems have been experienced following go live'. These have been captured by the programme team in a Ministerial briefing dated 27 January 2023; and

I found that 12 of the 16 recommendations made in the C&AG Report from October 2021 had been implemented with two not implemented, one partially implemented and one where further enhancements could be made.

Conclusions

  1. The ITS programme was launched in early 2020 and is intended to enable the Government to use modern, cloud-based systems for finance, human resources (HR), procurement and asset management. It forms one part of a significant investment being made by Government in digital modernisation.
  2. My review has identified some elements of good practice in the way in which the ITS programme has been managed. However, there is a need for Government to improve its management of strategic risks in major programmes, to ensure that sufficient specific business-unit level approval of functionality is gained prior to go live' and to enhance its processes to monitor the realisation of the benefits expected to be delivered over a sufficiently long time-span.

Objectives and scope of the review

  1. This review has evaluated:

the arrangements established to manage and monitor the implementation of the recommendations contained in the C&AG's 2021 report

the progress the Government of Jersey has made in implementing the agreed recommendations

the progress being made in implementation of releases one and two against recognised good practice. This will include assessment of the readiness for service of the two phases including:

  • the preparations for monitoring benefits realisation against the business case; and
  • the effectiveness of planned and implemented testing strategies; and

whether lessons are being learned from releases one and two in the planned programmes for subsequent releases.

  1. The review has considered the operation of the ITS programme to the end of November 2022 as well as the go live' decision at the end of December 2022. I have not reviewed the detailed functionality and operation of the ITS programme since releases one and two went live in January 2023.

Detailed findings

Framework for review

  1. Major ICT programmes are high cost, high profile and carry great uncertainties and risks. Experience from the public sector in many jurisdictions is that often such programmes fail to deliver their objectives in terms of cost and/or outcomes.
  2. My Report ICT Cloud Implementation – Integrated Technology Solution (October 2021) considered the ITS programme up to the end of August 2021 against a framework developed by the UK National Audit Office, as shown in Exhibit 1.

Exhibit 1: Framework to review programmes

Delivery Programme  variation and

Purpose Value set up management

Purpose: Is there a strategic need for the programme and is this the right programme to meet the business need?


Value:  Programme Does the  set-up: Is the programme  programme provide  set up in value for  accordance money?  with good

practice

and are risks being well managed?


Delivery and variation management: Are mechanisms in place to deliver the intended outcomes and respond to change, and is the programme progressing according to plan?

Source: National Audit Office: Framework to review programmes Update April 2021

  1. This review has followed up on my October 2021 Report and has considered the ITS programme up to the end of December 2022 against the same framework.

Purpose

  1. As noted in my 2021 Report, the quality of project initiation is highly predictive of project success. At the outset, it is essential to be clear on what objective the programme is intended to achieve and how the programme links to strategic priorities. In 2021 I considered the purpose of the ITS programme against three criteria:

need for the programme – is it clear what objective the programme is intended to achieve?  

portfolio management and dependencies – does the programme make sense in relation to the Government's strategic priorities?

stakeholder engagementhave the right people bought into the need for the programme?

  1. I made three recommendations in this area. Progress in implementing these recommendations is summarised in Exhibit 2.

Exhibit 2: Progress in implementing 2021 recommendations relating to purpose Recommendation Current Position  Evaluation

R1 Document an  A draft Technology Strategy has  Not yet implemented overall IT strategy for  been prepared. Further work is

the States of Jersey. being undertaken on this draft

Strategy. A final Strategy is yet to

be agreed and published.

R2 Provide clearer  The standing agenda for the twice- Implemented reporting to the ITS  monthly ITS Programme Board

Programme Board on  now includes a review of actions

the links between  from the last meeting, items for

project risks,  Board attention and the top risks interdependencies  and issues. The risk analysis is

and the overall  based on a heat map' which rates

project plan.  risks in relation to probability and

impact.

Recommendation Current Position  Evaluation R3 Ensure the  The stakeholder Communications  Implemented

Communication Plan  Strategy has identified and

for the ITS  segmented specific groups and

programme  teams to enable targeted

documents more fully  communications.

the communication

needs of the States

Assembly and

Scrutiny Panels and

how these needs will

be met.

Source: Jersey Audit Office analysis

  1. The ITS programme remains an essential element to the future stability of business operations of the States of Jersey. The previous applications used for finance were out of date and therefore unsupported and represented a strategic risk in relation to adopting modern business processes and reducing cyber security risks.
  2. However, as noted in my 2021 Report, neither the Outline Business Case (OBC) nor the Full Business Case (FBC) for ITS articulate clearly the link between the ITS programme and other active programmes aimed at modernising Government services.
  3. I noted in my Report in 2021 that it is essential that all elements of digital modernisation are considered as a portfolio and that dependencies between the programmes are identified formally and managed effectively. I therefore recommended that an overall IT Strategy is documented for the States of Jersey.
  4. Following the publication of my Report in 2021, a Technology Strategy was drafted during 2022. This draft is being considered currently with further work being undertaken by officers working alongside the Assistant Chief Minister responsible for Digital.
  5. The draft Technology Strategy sets out the current position of ICT in the States as shown in Exhibit 3, in relation to what is expected of a modern government and where Jersey is today.

Exhibit 3: Extract from the draft Technology Strategy

Source: Government of Jersey draft Technology Strategy

  1. The draft Technology Strategy sets out a long-term plan for how the Government intends to manage its technology portfolio.

Recommendations

R1  Finalise and publish the Technology Strategy.

R2  Prepare and publish six-monthly update reports on progress in implementing the

Technology Strategy.

Value

  1. My 2021 Report considered whether the ITS programme has been established to deliver value using the following criteria:

option appraisal – does the option chosen meet the programme's objective and provide long-term value?  

business case – does the business case demonstrate value for money over the lifetime of the programme?

cost and schedule – has the programme built up robust estimates of cost and schedule, including all programme components?  

benefits – does the programme: have a baseline; know what measurable change it is going to make; and measure it? Are benefits being achieved?

  1. I made two recommendations, one of which was applicable across Government and one of which was specific to the ITS programme. Progress in implementing these recommendations is shown in Exhibit 4.

Exhibit 4: Progress in implementing 2021 recommendations relating to value Recommendation Current Position  Evaluation

R4 Provide clearer  The 2022 version of the Outline  Implemented partially guidance and  Business Case template requires  but further work is templates to capture  the anticipated costs and benefits  required to make the all expected costs of  to be identified for a five-year  Outline Business Case major projects at the  period. Depending on the project  template fit-for-purpose Outline Business Case  and the time taken for benefits to  for long-term

stage.  be capable of realisation, this time  programmes.

period may be inappropriate.

In addition, the template asks for revenue and capital costs to be identified separately but does not provide a pro-forma for these two categories of cost to be separated.

Recommendation Current Position  Evaluation R5 Document and  There is an ITS benefits register  Implemented

implement a clearly  which has identified 92 benefits,

defined strategy to  along with their categorisation

measure, monitor and  (including financial, non-financial

report on whether the  and risk reduction) and nominated

ITS programme is  benefits owner. Many of these

delivering the  benefits will be delivered in the

intended financial and  future and this provides a

non-financial benefits  framework for tracking the benefit

and outcomes.  realisation.

Source: Jersey Audit Office analysis

  1. I have not considered options appraisal or the OBC and FBC as part of this follow up review as these aspects were considered fully in my 2021 Report.

Cost and schedule

  1. At the time of my initial fieldwork in November 2022, the expected programme cost was £62.52 million, of which £42.36 million had been consumed. At that time, the overall programme cost was aligned to the cost predicted in the FBC of £62 million.
  2. The FBC cost covers the period 2020-2026 (seven years), but the programme will close in 2023 when the system is fully live. It is however important that the Government continues to monitor benefits realisation beyond the programme closure.
  3. One area of particular strength in the operation of the ITS programme relates to delivery and variation management, specifically the monthly reporting to the programme's SOB.
  4. The role of the SOB is to ensure that:

the overall design principles, operating model and scope are maintained throughout the programme

the impact of any changes to or exceptions to design principles, operating model and scope is fully understood and justifiable; and

the programme remains financially viable.

  1. The SOB provides feedback to the Programme Board and approves the relevant change requests, prior to ratification at the Partnership Board.
  1. The reporting to the SOB demonstrates strong management of consumed and predicted financial resources including detailed scrutiny of the delivery partner.
  2. The reporting model adopted for the SOB and the strong financial management and governance which it demonstrates should be considered for future programmes.
  3. Notwithstanding the reporting model adopted, there remain cost pressures within the programme driven by post go-live issues identified.

Benefits

  1. In relation to value, the programme's objectives are principally to provide a modern and supported business platform rather than to deliver financial benefits. The FBC projected financial benefits of £1.8 million per year from 2024 onwards.
  2. The initial approach to benefits management adopted by the ITS programme meant that there was an insufficient central focus on the quantification and realisation of expected benefits. The approach adopted did not enable the measurement and quantification of benefits at a whole of Government level.
  3. Since my 2021 Report, the ITS programme has developed a more robust approach to benefits identification and monitoring. A total of 92 specific benefits are being tracked with a detailed Benefits Owners Guide detailing the characteristics of the benefit. Responsibility for the realisation of benefits is allocated to specific officers with the nature of the benefit (including financial, non-financial, and risk reduction) being identified.
  4. It is apparent however that many of the financial benefits which were identified in the FBC will either not be realised or their realisation will be delayed. For example, the £3 million total attributable savings relating to benefits that would be facilitated within the Commercial Services Transformation aligned to business process efficiencies are now not expected to begin to be realised until 2026. In addition, some of the expected savings from the decommissioning of the previous system may be lost if the system has to be retained as read-only or in any other form. The ITS programme should ensure that the Government is updated annually with details of how benefits realisation is predicted to vary from the expectations set at programme commencement.
  5. The Government has de-coupled longer-term benefits realisation from the ITS programme, with the programme closing at the end of 2023. The result is that programme-level responsibility and monitoring for any benefits realisation beyond 2023 will cease. The formal arrangement for the oversight and governance of the realisation of benefits beyond 2023 is unclear. In addition, ITS-related benefits are not planned to be tracked beyond the end of 2026. Given the long-term

investment in the new applications and the slower realisation of benefits than originally expected, I would expect the formal monitoring and reporting of benefits to be extended to 2030 if best practice is to be demonstrated.

  1. In my view, business cases should take account of long-term benefit realisation beyond the closure of the implementation programme and should adopt a seven or 10-year benefit measurement horizon, which is then reported-on formally. For major programmes with long-term implementations, a 10-year horizon should be the standard.

Recommendations

R3  Ensure that the monitoring and communication of benefits realisation is a

centralised responsibility that endures beyond the closure of the ITS programme and continues to 2030.

R4  Produce annual reports on benefits realisation from closed programmes to allow

transparent reporting on long-term benefit realisation.

R5  Include a 10-year cost and benefit horizon in all business cases for major

programmes with long implementation timescales.

Area for Consideration

A1  Use the reporting model adopted for the Strategic Oversight Board and the strong

financial management and governance which it demonstrates, for future programmes.

Programme set up

  1. As noted in my 2021 Report, a pre-condition for successfully starting a project and running an effective competition for commercial partners is that everyone involved in delivering the project clearly understands what must be delivered, and when. Immature or incomplete specifications lead to scope creep and confusion across the supply chain and make it difficult to incentivise commercial partners to deliver effectively and to hold them to account for any subsequent shortcomings.
  2. My 2021 Report evaluated the following elements of programme set up:

governance and assuranceare there structures (internal and external) which provide strong and effective oversight, challenge and direction?

leadership and culture – does the programme have strong leadership with the necessary authority and influence?  

resourceshas the organisation allocated the resources (staffing, skills, equipment and so on) required to deliver the programme?

putting the programme into practice – are scope and business requirements realistic, understood, clearly articulated and capable of being put into practice?

risk management – are key risks identified, understood and addressed?

  1. I made six recommendations in respect of programme set up in my 2021 Report. Progress in implementing these recommendations is shown in Exhibit 5.

Exhibit 5: Progress in implementing recommendations in respect of programme set up

Recommendation Current Position  Evaluation R6 Document clearly  Changes have been made to the  Implemented

the roles and  terms of reference of various

responsibilities of  boards in line with the

individual members of  recommendation.

groups in the

governance structure

together with the

accountability and

decision making

responsibilities for all

project activities and

deliverables.

R7 Improve the  The governance forums record the  Not implemented minutes of the  key actions, decisions and

meetings of boards  escalations within the governance

within the governance  forums. There is though no

structure and ensure  requirement to provide detailed

that they include a  minutes.

record of all agenda

items.

R8 Enhance the level  The SOB receives information  Implemented and detail of financial  relating to programme financial

information reported  information and supplier

to the ITS Partnership  performance. The information

Board.  provided is detailed and

independent of suppliers. I

consider this to be a satisfactory

forum for receiving such

information.

R9 Document more  The notes recorded in governance  Implemented formally the matters  forums now describe actions,

that have been  decisions and escalations. Any

escalated between  escalation acknowledges to which

groups within the ITS  forum it is escalated.

governance structure.

R10 Reassess the  This is now covered by the monthly  Implemented level of internal  SOB which determines what

resources dedicated  change controls are required to

to the ITS programme  the internal and external resources

and ensure that the  devoted to the programme. In

programme  addition, the Programme Board

timescales set are  reports identify the key risks and

realistic in light of the  how they will be mitigated.

resources actually

available.

R11 Ensure the ITS  The ITS Programme Board twice- Implemented but Programme Board  monthly report provides strong  enhancements could be and the ITS  evidence that this  made

Partnership Board  recommendation has been

reporting clarifies the  implemented.

relationship between  The ITS programme has stated that

the overall

programme status  it aProdgrahemmres to te Mh ane C agemorporenatt e O  ffice

and the status of key

component parts of  (RedCPM/AOm) bguer/idGanreceen on ( RA as Gse ) statssin ug t s onhe  

the programme. This

should include any  pevalurograatmmed thie ps guerfoidrmanancec e. I have

assumptions being  good practice from the  against

made regarding  Infrastructure and Projects UK's

future activities that

lead to the overall  Arevuthoritiew my'es prtho ogdolramogyme . I conassur sidan erce  

programme status

being reported more  that enhanthcee gud toid anproce vi  coude a ld wbideer

favourably than a key  assessment of programme

component part of the  performance.

programme.

Source: Jersey Audit Office analysis

  1. My fieldwork for this follow up review confirmed that the overall programme management is strong. The expected elements of good practice were in place, with an experienced and effective programme manager and strong programme communications. An example of this was the user experience venue in a dedicated facility. This facility allowed end-users to be walked through the new systems and business processes.
  2. Additionally a business change network of around 350 officers across the States of Jersey was put in place with demonstration roadshows organised. A 'just-in-time' approach was adopted in respect of training requirements which is not unusual for a programme of this nature.
  3. Project level risk management was working effectively at a detailed level at the time of my fieldwork. There was clear evidence of detailed project risks being recorded, escalated and mitigated. However the key strategic risks in relation to the programme were not evident in the documentation provided. The strategic risks of the programme that I would have expected to have been documented as the programme progressed include:

the risks associated with the continued adoption of a big bang' approach to implementation for the whole of the States of Jersey rather than adopting a phased implementation by functional area or department. While a big bang'

approach simplifies data migration to the new systems, a phased implementation would have allowed teething problems' to be identified and resolved without affecting the whole of the States of Jersey. I understand that the decision to adopt a big bang' approach was taken as part of the procurement stage of the project, after discussion of the relevant benefits and risks of various implementation strategies with the prospective delivery partners. However I would have expected the risks associated with this approach to have continued to have been considered as the programme progressed

the risk of the lack of formal, tested, contingency plans should it be necessary to revert to previous systems; and

the risks that were evident in the progress of the transition of the existing Supply Jersey users to the new SAP Ariba procurement system.

  1. In November 2022, Internal Audit conducted a review of user access roles in the test system and made a number of observations and recommendations. The management response to these recommendations appears to treat the observations and recommendations seriously.

Recommendations

R6 Ensure that the key strategic risks associated with programmes are identified,

recorded and managed.

R7 Enhance the CPMO guidance on programme performance to have greater

alignment with wider best practice such as the UK's Infrastructure and Project Authority's programme review methodology.

Delivery variation and management

  1. I have considered the arrangements within the ITS programme for delivery variation and management. In doing so, I have considered specifically:

delivery strategy are there appropriate incentives for all parties to deliver (contractual, performance management or other)?

change control – is there an effective mechanism to control programme alterations?

responding to external change – is the programme sufficiently flexible to deal with setbacks and changes in the operating context?

performance management – is progress being measured and assessed, including consideration that the programme is still the right thing to do?

lessons learned – is the programme learning from experience on the current programme and previous relevant programmes?  

transition to business as usual – does the programme have a clear plan for transfer to operations/business as usual?

  1. I made five recommendations in respect of delivery variation and management in my 2021 Report. Progress in implementing these recommendations is shown in Exhibit 6.

Exhibit 6: Progress in implementing recommendations in respect of delivery variation and management

Recommendation  Current Position  Evaluation R12 Develop the  The SOB has now been  Implemented

reporting of overall  established as the most senior

progress to the ITS  governance forum for the ITS

Programme Board  programme. Key members of the

and the ITS  other boards are on the SOB.

Partnership Board to  Reporting to the SOB has

align cost and delivery  addressed this recommendation.

indicators in assessing

overall programme

performance.

Recommendation  Current Position  Evaluation

R13 Report formally  The SOB is presented with a  Implemented the performance of  monthly review of supplier

third-party partners  performance and this complies

against agreed Key  with expected good practice. This

Performance  information is not shared with the

Indicators (KPIs) to the  Partnership Board but there is

ITS Partnership Board.  representation from key members

of this board on the SOB.

R14 Develop the  The SOB is presented with a  Implemented change request  monthly review of change control

reporting to include  requests and this complies with

clear cost implications  expected good practice.

associated with each

individual change

request.

R15 Revisit the  The recommendations in the  Implemented lessons learned log  lessons learned log have been

from the Revenue  considered by the ITS programme.

Jersey Transformation

Programme and

ensure all actions in

the log have been

considered and

mitigating actions are

in place for the ITS

programme.

R16 Ensure that  The responsibility for benefits  Implemented responsibility for  realisation has been allocated and

benefits realisation is  there is clear evidence that the

identified and  expected benefits have been

allocated to specific  categorised and that a framework

business units within  for benefits realisation tracking is

departments.  in place.

Source: Jersey Audit Office analysis

  1. At the time of my 2022 fieldwork, Release One (Connect Finance, Connect Inventory and Connect Suppliers) and Release Two (Connect People) of the ITS programme were planned to go live' at the beginning of January 2023. This is nine months later than had been forecast in the original programme plan. A decision was however made during 2022 to de-couple releases one and two, with the majority of Release Two subsequently planned to go live' at the end of January 2023.
  1. In my view, the imperatives of achieving planned simultaneous release dates for both releases were prioritised over lower-risk phased deployments which have a lower capacity impact on the end-user community.
  2. The full implications of releasing major functionality, in particular in relation to the impact on the end-user community, should be more fully assessed and the risks and benefits of doing so clearly set out for governance-level decision making.
  3. One of the key imperatives of the ITS programme was to minimise bespoke configuration of the applications being implemented. Achieving this imperative has critical implications for the scope and complexity of the testing and user acceptance processes. The introduction of bespoke functionality means that additional testing is required to determine whether other elements of functionality have been affected by the change.
  4. One of the things that was produced to inform the decision to go live' was a Business Readiness Checklist. This Checklist identified the critical activities which must be completed before the go live' decision was made. I have a number of reservations however about the effectiveness of this document in relation to business-unit acceptance and sign-off of specific functionality. In particular, the Business Readiness Checklist did not focus sufficiently on specific business areas such as health and police, but instead presented a global view of functionality (for example finance and HR) as a whole. The meant that some of the nuances of differences in how specific business areas operate was not assessed adequately.
  5. In addition, in the version of the Business Readiness Checklist dated 22 December 2022, 21 out of 100 sub-categories in relation to the RAG status were rated as Amber'. Given the quantity and potential impact of these sub-categories, it is not clear in the documentation provided to us how these were assessed further prior to the decision to go live'.
  6. In October 2021 a document was produced that captured the lessons learned in relation to testing releases one and two at that time. This contained an impact analysis of these lessons for release three. The document we were provided with as evidence has not been updated since October 2021, although post go live' lessons learned have been captured.
  7. In practice, several problems have been experienced following go live'. These have been captured by the programme team in a Ministerial briefing dated 27 January 2023.

R8  Ensure business readiness checklists for future releases include a service-related

dimension which provides evidence that each significant service area across the States of Jersey is satisfied that the functionality has been tested and signed off as meeting business needs.

R9 Review the lessons learned documents to ensure they have captured all lessons

learned in a single consolidated document.

R10 Develop a clearly documented plan to prevent the issues and problems from

releases one and two being repeated for future ITS releases and in future Government programmes.

Audit Approach

The review included the following key elements:

review of relevant documentation provided by the Government of Jersey; and

interviews with key officers within the Government of Jersey.

The documentation reviewed included the:

Business Readiness Checklist and Connect Go-Live Decision supporting information

C&AG Recommendations Tracker

Connect Get Started Guide

draft Technology Strategy

Governance Boards Proposed Changes to Terms of Reference

ITS Benefit Owners Guide and ITS Benefits Register

ITS Communications Strategy and Delivery Plans

ITS Full Business Case

ITS Lessons Learned Log

ITS Ministerial Briefing of 27 January 2023

ITS Programme Received Assurance Inputs Log

ITS RAG Guidance and Calculator

ITS Risks and Issues Dashboard

Outline Business Case 2022 template

Presentations to the ITS Programme Board

Presentations to the ITS SOB

The following people contributed information through interviews or by correspondence:

Chief Internal Auditor

Chief Operating Officer

Group Director for People and Corporate Services

Group Director, Integrated Services, Commissioning and Social Care

Head of Business Support

Head of ITS Commercial and Financial Management

Head of the Intelligent Client Function

ITS Programme Manager

Treasurer of the States

The fieldwork was carried out by an affiliate working for the Comptroller and Auditor General.

Summary of Recommendations and Area for Consideration

Recommendations

R1  Finalise and publish the Technology Strategy.

R2  Prepare and publish six-monthly update reports on progress in implementing the

Technology Strategy.

R3  Ensure that the monitoring and communication of benefits realisation is a

centralised responsibility that endures beyond the closure of the ITS programme and continues to 2030.

R4  Produce annual reports on benefits realisation from closed programmes to allow

transparent reporting on long-term benefit realisation.

R5  Include a 10-year cost and benefit horizon in all business cases for major

programmes with long implementation timescales.

R6 Ensure that the key strategic risks associated with programmes are identified,

recorded and managed.

R7 Enhance the CPMO guidance on programme performance to have greater

alignment with wider best practice such as the UK's Infrastructure and Project Authority's programme review methodology.

R8  Ensure business readiness checklists for future releases include a service-related

dimension which provides evidence that each significant service area across the States of Jersey is satisfied that the functionality has been tested and signed off as meeting business needs.

R9 Review the lessons learned documents to ensure they have captured all lessons

learned in a single consolidated document.

R10 Develop a clearly documented plan to prevent the issues and problems from

releases one and two being repeated for future releases and in future Government programmes.

Area for Consideration

A1  Use the reporting model adopted for the Strategic Oversight Board and the strong

financial management and governance which it demonstrates for future programmes.

26 | Integrated Technology Solution – Follow Up