Skip to main content

Dates and Minutes of all the meetings to scope the Environment Impact Assessment for the Energy from Waste plant

The official version of this document can be found via the PDF button.

The below content has been automatically generated from the original PDF and some formatting may have been lost, therefore it should not be relied upon to extract citations or propose amendments.

1240/5(4263)

WRITTEN QUESTION TO THE MINISTER FOR PLANNING AND ENVIRONMENT BY THE DEPUTY OF ST. MARY

ANSWER TO BE TABLED ON TUESDAY 24TH FEBRUARY 2009

Question

Could the Minister provide the Assembly with the dates and the minutes of all the meetings held to scope the Environment Impact Assessment for the Energy from Waste plant?

Answer

EIA procedures in Jersey are governed by the Planning and Building (Environmental Impact) (Jersey) Order 2006 which came into force on 30th October 2006. A project falling within Schedule 1 of this order is required to submit an Environmental Impact Statement in accordance with Schedule 2.

The Order provides at article 4 that the Minister may indicate scope of environment impact statement'. This is done where the applicant makes a request to the Minister as set out in Article 5 of the Order. This is not a mandatory step and the applicant is entitled to use their own judgement on what scope the Environmental Impact statement should cover and to take the risk that this will be considered sufficient when they submit this with their application.

Prior to the enactment of the Order on 30th October 2006 the Department operated a system by which there was a consultative based approach to arrive at an agreed Scoping Report which identified key issues.

In the case of the proposed EFW there was never any doubt, because of the size and nature of the plant, that it would require EIA. The process was initiated in November 2005 with a pre-scoping report prepared by Babtie Fichtner which set out the range of possible issues that would need to be considered. This document formed the basis of subsequent information gathering conversations with officers in the Environment Department, the Planning Department, TTS Transport and Health Protection to further develop the scoping.

These conversations are noted in the table of Consultee meetings that forms Appendix 1 to the Environmental Impact Statement. The purpose of these meetings was for Babtie Fichtner and their client TTS, to gain a more informed view of existing information and how well the pre-scoping report addressed the likely significant impacts of the plant and minutes were not taken by officers of the Department

The final agreed scope is referred to in the letter on the 4th May 2006 from the Policy Manager to TTS (attached). The scope referred to was arrived at by way of a workshop session on the 3rd April that identified the relevant issues. The minutes' of that workshop are reflected in the attached information Scoping Issues for Proposed Energy from Waste Facility at La Collette – Flipchart Notes'

Attachments.

Pre scoping report 17th November 2005 (see attached word file)

Appendix 1 of the Environmental Impact Statement (see attached word file)

Letter of 4th May 2006

Workshop flip chart notes (the agreed scoping referred to in letter of 4th May 2006)

Addendum

Once an Environmental Impact Statement is submitted accompanying a planning application, the statement is scrutinised by the Department as well as being publicly advertised through the normal planning process, including direct consultation with relevant statutory, government and public bodies. Thus if a significant issue had been overlooked there is a further opportunity for the Department, consultees and other interested parties to identify this.  Under Article 6 of the Planning and Building (Environmental Impact) (Jersey) Order 2006, the Minister is able to require any further issues to be considered.

The  public  advertising  process  for  the  planning  application  and  the  accompanying  Environmental  Impact Statement for the Energy for Waste plant began on 17th January 2007 and representations were accepted up until the public Ministerial Meeting on 19th October 2007. During this 10 month consultation period, no concerns were raised about the methodology or scope of the Environmental Impact Assessment.

Environment and Public Services Environment Department

Howard Davis Farm, La Route de la Trinite Trinity , Jersey, JE3 5JP

Tel: +44 (0)1534 866200

Fax: +44 (0)1534 866201

Quintin Murfin 4 May 2006 Principal Engineer

Transport and Technical Services

South Hill

St Helier

JE2 4US

Our ref: ESU/11/01/01 Your ref:

Dear Quintin,

EfW and Composting Waste Management Facilities: EIA confirmation of scope

Further to this morning's meeting, I would like to confirm that I am happy with the scope of the Environmental Impact Assessments identified for both the Energy from Waste facility and the composting facilities as developed to date.  Clearly, final site selection for both facilities is dependent not just on environmental issues and will be an important determinant in the final emphasis of each of the elements that need to be presented in the final Environmental Statements.

Whilst it is important to recognise that the Planning and Environment Department operates in a regulatory role for the EIA process, the flexible and co-operative approach that we have engaged in so far has been very productive in enabling the scope to evolve as the process develops and other factors are considered.  I look forward to continuing in this manner as the project develops further.

Yours sincerely,

Sarah Le Claire Policy Manager

direct dial: +44 (0)1534 866214 email: s.leclaire@gov.je www.env.gov.je

Scoping Issues for Proposed Energy from Waste Facility at La Collette Flip Chart Notes Re-visited Notes 03/04/06 QM/SED/SLeC)

 

Issue

New site at La Collette

Hazard assessment

Fire

Explosion (dust / gas)

Dust release

Spillage

Toxic gases

Residue disposal - hazards

Starter fuel / ignition

Heat release

Explosion (boilers etc)

Fire fighting effluents

Steam

Fire fighting / incident

Access provisions

TO BE CARRIED OUT

Cultural Heritage and property issues

Property values statement

Loss of income - statement

Sterilisation of disposal sites - statement

Heritage – statement

Archaeology scope out

SEEN AS SCOPED OUT

Landscape

Visual impact assessment UNDERWAY

Planning

Planning context assessment

Island Plan assessment

Waterfront Plan assessment

Interaction with other facilities – e.g. major incident / petroleum / gas / power station

NEED TO REFER TO EAST OF ALBERT ETC.

Sustainability

CO2 emissions and climate change

Operation evaluation

Construction evaluation

Transport fuel use statement Material resources statements on

Construction materials

Displaced infill disposal

Construction waste

Old plant demolition

Fly ash includes disposal sites

Bottom ash

Demolition and decommissioning

Waste hierarchy - statement

TO BE DEVELOPED

Water Resources

Groundwater scoped out

Surface water disposal statement

Coastal waters scope out

Flood risk management – coastal assessment  (climate change)

Water supply statement

Waste water / sewerage statement

NO CHANGE

Ground Conditions Soils scope out

Agriculture scope out

Contaminated land statement

Ground conditions statement

Geology statement

NO CHANGE

Land use Recreation and amenity – statement

Shoreline statement

NO CHANGE

Waste licence EIA Draft Working Plan – being developed in conjunction with Willie

Peggie

Odour and air quality Statement on odour and air quality

Dispersion modelling

Traffic impact

Fog / mist

MODELLING PLUS CRITIQUE

Noise Operation

Traffic assessment

Plant noise and vibration assessment

Shredding noise assessment

Construction noise assessment

Construction traffic assessment

Piling noise and vibration

FURTHER DISCUSSIONS WITH STEVE SMITH PENDING Biodiversity Ramsar site cooling water plume statement

Airborne emissions

Flora and fauna scoped out

Habitat

Microclimate scoped out

REPORT FROM DAVID FEE RECEIVED

Construction Statement on:

Population

Employees (local)

Existing population

Proximity & numbers

D & B contractor's staff

Construction Village

Operation Statement on:

Population

Employees (local)

Existing population

Proximity & numbers

Health impact Stakeholders

assessment Facility users

Population in vicinity (residents)

Workers not included covered under H&SatW

Effects during Construction

Emissions

Visual

noise

dust

traffic

light

Effects during operation

Working hours

Emissions

Traffic

Light

Dust

HEALTH IMPACT ASSESSMENT TO BE DEVELOPED WITH STEVE SMITH

Transport operation Traffic – baseline and traffic generation

Refuse

Collection vehicles

Transfers from CA

Export of recyclables

Employees and maintenance

JERSEY WASTE STRATEGY TRAFFIC IMPACT STUDY CARRIED OUT REPORT APRIL 2006

Other issues statements on

Outward shipping

Guernsey waste import? traffic and shipping

Local HGV access

Pedestrian / cycle route from Havre des Pas

Travel plan

La Collette development

Future access strategy

NO CHANGE

Transport - Construction traffic generation study

construction Statements on

Works area

Parking

Plant import road and shipping

NO CHANGE