Question

"Will  the Minister  provide details of all  the agreed allocations  made to  date from the Economic Stimulus Package?"

Answer

All allocations from the Economic Stimulus Package are made by ministerial decision and are publicly available with their accompanying reports. To date the agreed allocations are:

Ministerial Department Projects £

Decision

Reference

MD-TR-2009- 0110

MD-TR-2009- 0130

MD-TR-2009- 0131

MD-TR-2009- 0135

MD-TR-2009- 0133

MD-TR-2009- 0141 MD-TR-2009- 0143 MD-TR-2009- 0132

MD-TR-2009- 0142 MD-TR-2009- 0153


TTS Treasury

ESC

Social Security EDD

EDD

TTS

Social Security

Jersey Harbours TTS


Design spend on projects in provisional 200,000 programme

Programme Management costs - estimate 200,000 included in provisional programme

Up to 100 additional places at Highlands (first

academic year), Careers Strengthening annual 924,200 cost new adviser and first tranche training

allocation, Advance to Work (Youth Training)

annual cost staff including 3 mentors (sufficient

for 45 participants) and IT set up

Citizens Advice Bureau grant for debt 50,300 counselling and mortgage arrears protocol

First tranche of funding for various initiatives to 500,000 support businesses

States Apprenticeships Scheme 972,750 Promenade and Cycle Track 337,000 Transitional relief from HIE to Income Support - 1,440,000

extension of 100% support

Design spend on St Aubins Pier project 70,000 Victoria Avenue Phase 2 - Fiscal Stimulus 1,143,452

contribution to construction cost

MD-TR-2009- TTS Drainage and highways projects - pre-tender 263,000 0154 costs of design and professional fees

MD-TR-2009- Housing Planning spend for Housing Backlog 133,200 0161 Maintenance programme

Total of approved allocations to Departments – "Green Lights" 6,233,902 Provisional "amber light" approvals 40,575,985

TOTAL PROVISIONAL PROGRAMME 46,809,887