Skip to main content

Procurement savings

The official version of this document can be found via the PDF button.

The below content has been automatically generated from the original PDF and some formatting may have been lost, therefore it should not be relied upon to extract citations or propose amendments.

1240/5(8278)

WRITTEN QUESTION TO THE MINISTER FOR TREASURY AND RESOURCES BY DEPUTY R.G. LE HÉRISSIER OF ST. SAVIOUR

ANSWER TO BE TABLED ON TUESDAY 29th APRIL 2014

Question

Could the Minister identify the running costs of the Corporate Procurement section in each of the last three years and identify the promised savings and actual savings made in each of those years?

Answer

The Minister is pleased to have this opportunity to address recent publicity following the publication of the  Comptroller  and  Auditor  General's  report  on  Corporate  Procurement,  including  the  perception apparently (and mistakenly) held in some quarters that the Unit is costing more than it delivers in savings.

Savings are only one measurement. The benefits of a professional procurement unit extend far wider and include:-   Probity,  good  governance,  legal  framework  ,  risk  management   and  an  open,  fair  and transparent framework in which goods and services are competitively tendered and organisational goals achieved. The C&AG recognises the progress made in all of these areas.

The table below sets out the running costs for 2011 to 2014 and the savings achieved.  

 

 

2011

2012

2013

2014

Total Cumulative Savings and Cost

2011-2014

Savings Achieved by Financial Year

£60,801

£60,801

£60,801

£60,801

 

 

 

£752,908

£752,908

£752,908

 

 

 

 

£2,240,649

£2,240,649

 

 

 

 

 

£3,451,300

 

Total Cumulative Annual Saving by end of year

£60,801

£813,709

£3,054,358

£6,505,658

£10,434,526

Less Cost

-£473,000

-£676,740

-£903,180

-£915,682

-£2,968,602

Net Benefit

-£412,199

£136,969

£2,151,178

£5,589,976

£7,465,924

At the start of the Comprehensive Spending Review (CSR) period in 2011 a number of procurement projects were initiated and by the end of 2012 a proportion of these projects were in progress and savings were being identified. £3.05million was removed from Departmental base budgets in 2013.

Further  procurement  projects  were  delivered  in  2013  resulting  in  savings  of  £2.1m.  An  estimated £570,000 of these savings will come from projects to be delivered during 2014.

In late 2013, it was evident that by 2014 total budget reductions of around £5.1 million could be made. Further procurement savings had been recorded by Corporate Procurement but these savings could not be fairly attributed to Departments because the savings were either non- recurring or because the base budgets for the goods and services do not exist.

In order to address this issue and make up the savings target of £6.5million, £1.4million has been taken out of Departmental inflation budgets. This was possible due to lower inflation than budgeted for in 2013. A total of £3.45 million will be removed from Departmental budgets during April 2014.

The annual cost of the Corporate Procurement section in 2013 was £903,180 and annual savings in excess of £6.5million (cumulative savings of £10,434,526) have enabled permanent budget reductions.