Skip to main content

(9452) The installation by JT of fibre-optic broadband

The official version of this document can be found via the PDF button.

The below content has been automatically generated from the original PDF and some formatting may have been lost, therefore it should not be relied upon to extract citations or propose amendments.

1240/5(9452)

WRITTEN QUESTION TO THE MINISTER FOR TREASURY AND RESOURCES BY THE DEPUTY OF ST. JOHN

ANSWER TO BE TABLED ON TUESDAY 24TH MAY 2016

Question

Can the Minister, as shareholder representative, provide an up-to-date account of the fibre installation being carried out by JT and advise how many of the employed engineers for this project are now sourced locally?

Answer

The fibre installation is progressing as set out in the following table:

 

Network element

Broadband premises

Percentage complete

Core network

-

100%

Premises passed fibre network

34,272

100%

Premises connected fibre network

18,326

53.5%

The Minister is advised by JT that, as at 19th May 2016, there are 159 JT staff involved with the fibre installation programme. Of the 159 staff, there are 72 local engineers and 45 non-local engineers dedicated to the programme on a full time basis.

The Minister will soon be inviting all States' Members to the annual update from JT where all aspects of progress will be shared.