17

WQ.85/2019

WRITTEN QUESTION TO THE MINISTER FOR THE ENVIRONMENT BY DEPUTY K.G. PAMPLIN OF ST. SAVIOUR

ANSWER TO BE TABLED ON TUESDAY 12th FEBRUARY 2019

Question

Will the Minister set out a timeline in respect of the planning applications for the Future Hospital to show the length of time the planning process in relation to this project has taken to date, as well as the planning stages through which it has passed; and will he state, for each planning stage, which procedures apply to the processing of the application?

Answer

The tables below set out the timeline in respect of the two hospital planning applications, including dates and references to the Articles within the Planning and Building (Jersey) Law 2002 or subordinate legislation, for each stage of the application process.

17

FIRST APPLICATION (PP/2017/0990)

 

Date

Action

Wk

Relevant procedure

 

29 Jun 17

Application delivered

0

Planning and Building (Jersey) Law 2002

Art 9

17 Jul 17

Minister resolves to hold Public Inquiry

3

Planning and Building (Jersey) Law 2002

Art 12

20 Jul 17

Independent Inspector appointed

3

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 3

25 Jul 17

Announcement of Inquiry

4

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 5

17 Aug 17

Terms of Reference issued

7

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 4

8 Sept 17

Deadline for Statements of Case

10

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 5

22 Sept 17

Extended deadline for Statements of Case

12

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 5

10 Oct 17

Site visit

15

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 16

20 Oct 17

Deadline for Proofs of Evidence

16

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 9

6-10 Nov 17

Public Inquiry held

19

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 14

2 Jan 18

Inspector's Report submitted

27

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 17

9 Jan 18

Minister refuses application, applicant notified

28

Planning and Building (Jersey) Law 2002

Art 12 & 19

SECOND APPLICATION (PP/2018/0507)

 

Date

Action

Wk

Relevant procedure

 

13 Apr 18

Application delivered

0

Planning and Building (Jersey) Law 2002

Art 9

24 Apr 18

Minister resolves to hold Public Inquiry

2

Planning and Building (Jersey) Law 2002

Art 12

30 Apr 18

Independent Inspector appointed

3

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 3

15 May 18

Announcement of Inquiry

5

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 5

17 May 18

Terms of Reference issued

5

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 4

6 July 18

Deadline for Statements of Case

12

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 5

18 July 18

Revised Terms of Reference Issued (alternative sites)

14

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 4

24 July 18

Amended drawings received and re-advertised

15

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 4

2 Aug 18

Pre-Inquiry Meeting

16

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 8

28 Aug 18

Deadline for Proofs of Evidence (application)

20

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 9

7 Sept 18

Deadline for Proofs of Evidence (alternative sites)

21

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 9

17-21 Sept 18

Public Inquiry held

23

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 14

10 Dec 18

Inspector's Report submitted

34

Planning and Building (Public Inquiries) (Jersey) Order 2008

Art 17

14 Jan 19

Minister refuses application, applicant notified

39

Planning and Building (Jersey) Law 2002

Art 12 & 19