Hospital maintenance work

The official version of this document can be found via the PDF button.

The below content has been automatically generated from the original PDF and some formatting may have been lost, therefore it should not be relied upon to extract citations or propose amendments.

WQ.87/2019

WRITTEN QUESTION TO THE MINISTER FOR HEALTH AND SOCIAL SERVICES BY DEPUTY K.G. PAMPLIN OF ST. SAVIOUR

ANSWER TO BE TABLED ON TUESDAY 12th FEBRUARY 2019

Question

Will the Minister provide the list of maintenance work and any other vital building works that in his view is required to keep the current hospital running safely for the next 10 years?

Answer

Health and Community Services is in the final stages of completing a 6 Facet Building Condition Survey. This type of survey provides an industry standard' means of assessing the condition of the Jersey General Hospital estate with respect to 1) physical condition 2) functional suitability 3) space utilisation 4) quality 5) fire, health and safety and 6) environmental management.

A summary of backlog maintenance costs as of February 2019 is set out below. These costs are associated with maintaining statutory and regulatory compliance. They are currently going through a process of internal validation before a final report can be provided to the Health and Community Services Management Executive

 

All Blocks

 

 

 

 

 

 

 

 

 

Summary costs

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cost

 

Year 0

Year 1

Year 2

Year 3

Year 4

Year 5-10

Year 11-15

Works cost

£54,871,514

 

£21,632,588

£1,514,795

£1,891,026

£733,802

£511,352

£16,612,687

£11,975,265

Additional costs

£283,310

 

£283,310

£0

£0

£0

£0

£0

£0

(inc. Jersey %)

 

 

 

 

 

 

 

 

 

SUB TOTAL

£55,154,824

 

£21,915,898

£1,514,795

£1,891,026

£733,802

£511,352

£16,612,687

£11,975,265

PRELIMINARIES (20%)

£11,030,965

 

£4,383,180

£302,959

£378,205

£146,760

£102,270

£3,322,537

£2,395,053

CONTINGENCY/RISK (10%)

£6,618,579

 

£2,629,908

£181,775

£226,923

£88,056

£61,362

£1,993,522

£1,437,032

PROFESSIONAL FEES (11%)

£8,008,481

 

£3,182,188

£219,948

£274,577

£106,548

£74,248

£2,412,162

£1,738,809

 

 

 

 

 

 

 

 

 

 

OVERALL COST

£80,812,849

 

£32,111,174

£2,219,477

£2,770,731

£1,075,166

£749,233

£24,340,908

£17,546,159

 

 

 

Year 0

Year 1

Year 2

Year 3

Year 4

Year 5-10

Year 11-15

 

 

 

 

 

 

 

 

 

 

Cumlative Costs

Year 0

Year 1

Year 2

Year 3

Year 4

Year 10

Year 15

£32,111,174

£34,330,651

£37,101,382

£38,176,549

£38,925,782

£63,266,690

£80,812,849

These costs are associated with the General Hospital alone. The relatively large amount in Year 0' (£32m) reflects the accumulated deferred backlog maintenance. Much of this work was deferred because buildings were programmed for early demolition as part of the Future Hospital Project. These buildings will now need investment not previously considered. Further surveys will need to be undertaken for the remainder of the Health and Community Services estate including community and ambulatory services at Overdale Hospital and mental health and other services at St Saviour's site. There is also a significant number of individual Health and Community Services buildings across the Island whose condition will need to be surveyed.

They do not include the capital costs of other vital building works, particularly those associated with providing additional hospital bed, operating theatre or outpatient clinic capacity that will be needed to meet the demand created by the increasingly ageing demographic on the Island. Nor do they include any additional  costs  such  as  service  decant  and  temporary  buildings,  associated  with  enabling  backlog maintenance projects to proceed. The costs are current costs excluding the impact of inflation on any programmed works.

In conclusion, these costs set out in this written answer are likely to represent only the minimum costs required to keep the current General Hospital statutory and regulatory compliant for the next 10 years.