Skip to main content

Professional fees; design and consultant renumeration

The official version of this document can be found via the PDF button.

The below content has been automatically generated from the original PDF and some formatting may have been lost, therefore it should not be relied upon to extract citations or propose amendments.

WQ.338/2022

s

WRITTEN QUESTION TO THE CHIEF MINISTER

BY DEPUTY M.B. ANDREWS OF ST. HELIER NORTH QUESTION SUBMITTED ON MONDAY 12th DECEMBER 2022 ANSWER TO BE TABLED ON MONDAY 19th DECEMBER 2022

Question

“Further to the response to written question Written Question 305/2022 regarding the new Hospital project, will the Chief Minister provide a breakdown of the £43.5 million spent on professional fees, design, and consultant remuneration since 2019?”

Answer

The £43.5m figure represents expenditure to the end of September 2022. Updated figures below total £44.7m, which represent expenditure from inception of the Our Hospital project in May 2019 to end the of October 2022.

The breakdown for the professional, design and consultant remuneration since 2019 are shown in the table below:

 

Cost Categories

(£m)

Design and Professional Fees

9.6

Pre-Construction Service Agreement (PCSA) Costs

35.1

The Design and Professional fees of £9.6m included:

Health Planner & Clinical Design Team

Project Management Office

Cost Management Consultants

Design Quality Assurance and NEC Supervisor

Property & Planning Fees Consultants

Government of Jersey Project Team Costs

The Pre-Construction Service Agreement costs of £35.1m were for services including, but not limited to:

Feasibility Studies

Completed design and associated activities to reach the completion of RIBA Stage 3 design

Surveys

Building Information Modelling (BIM)

Provision of Cost Plans and PCSA Programme

Development of a Construction Programme

Contractual Administration

Planning Application Development and Submission

Community Engagement & Consultation

Given that this phase of the works has reached its end and the commercial relationship between the Government of Jersey and the Design and Delivery Partner has now ceased, there is no further expenditure anticipated on PCSA costs.