Dear Chair,
RE: Progress update – Bridging Island Plan Proposals
Thank you for your letter dated 22nd January 2025 regarding an update on the Bridging Island Plan proposals.
I have attached a separate document which has the details regarding the progress to date as of December 2024.
The current status of BIP proposals, as set out in the attached document, are as follows:
• Eight are complete (20%)
• 17 are in progress (42.5%)
• 12 have yet to commence (30%); and
• Three have been commenced but been subsequently deferred/ are held pending
If there is any further information that you require, then please do get in contact. Yours sincerely
Deputy Steve Luce
Minister for the Environment